Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 311 discussion

Actual exam question from PMI's PMP
Question #: 311
Topic #: 1
[All PMP Questions]

A project is in progress with a team that is new to agile approaches. After the first sprint review, the team performance begins slipping, and the conclusion is that there is not an adequate flow of work for the team.
What should the project manager do?

  • A. Provide the product owner with training.
  • B. Submit a change request to rebaseline the project.
  • C. Change the project approach to hybrid.
  • D. Discuss the issue with the stakeholders.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
3 weeks, 1 day ago
Selected Answer: D
I had a lot of trouble studying due to incorrect comment discussions. Even if the PO receives training, it will have no bearing on the team's performance. Issues must be discussed with stakeholders.
upvoted 1 times
...
ompk
4 months, 1 week ago
in Agile, workflow is a collective agreement approach by PO, development team, scrum master or the project manager. Workflow basically means sprint. in this case even if a new PO is going to be trained even still it states in the question that there is no adequate workflow for "The Team" option D is the right choice
upvoted 2 times
...
odylec
8 months ago
Selected Answer: D
D is the answer. You must always know the reason why something happent. If your PO needs training so maybe you must choose the team
upvoted 1 times
odylec
8 months ago
Discussing the issue with stakeholders aligns well with Agile principles and provides a platform for a collaborative solution. It allows for immediate feedback and the joint development of strategies to enhance team performance and work flow. However, the decision ultimately depends on the specific context of the project and the nature of the challenges faced by the team.
upvoted 1 times
...
...
Bruce_Liu
8 months, 1 week ago
Selected Answer: A
ChatGPT chooses A.
upvoted 1 times
...
josephsafiran
8 months, 2 weeks ago
Selected Answer: A
The project manager should A. Provide the product owner with training. In an agile approach, the product owner plays a crucial role in managing and prioritizing the backlog, ensuring a steady flow of work for the team. If the team is new to agile, it’s possible that the product owner may also need guidance or training to effectively fulfill this role. This could help improve the flow of work and enhance team performance
upvoted 1 times
...
Hashi1_snr
10 months, 3 weeks ago
Selected Answer: D
The chosen answer is absolutely correct. If we are to provide training here, it's not the PO that needs training but the team as it's team's performance that affected work flow. So to address the issue in this case, PM needs to discuss it with the stakeholders, including the PO, to agree on how to improve team's performance to meet the desired objective.
upvoted 2 times
...
Only12go
11 months, 1 week ago
Selected Answer: A
Discussing the issue with stakeholders (option D) can be a useful action in many situations. However, in the context of the question, the primary challenge appears to be related to the "flow of work" for the team within an agile framework. The product owner plays a crucial role in maintaining a prioritized product backlog and ensuring that there's a steady stream of well-defined and prioritized work for the development team. If the flow of work is inadequate, it's often a sign that the product owner may need more guidance, training, or support to effectively maintain the backlog and liaise between stakeholders and the development team.
upvoted 4 times
ChezQW
11 months ago
This was my exact train of thought why I chose A. However, maybe engaging the stakeholders may help the product owner further understand the requirements and then the product owner would be able to add to the product backlog and prioritize it. Maybe.
upvoted 2 times
...
...
adingmaki
11 months, 2 weeks ago
A. The PO is new. Most of the comments forgot this. Remember that the PO is what we call "the voice of the customer". He should go to the customer.
upvoted 2 times
...
Ebby21
11 months, 3 weeks ago
Selected Answer: A
According to chatgpt "A. Provide the product owner with training. In an agile project, the product owner plays a crucial role in prioritizing and managing the product backlog, ensuring there is a steady flow of work for the development team. If the team's performance is slipping due to an inadequate flow of work, it's essential to address this issue. Providing training to the product owner can help them better understand their responsibilities and how to manage the backlog effectively. It can lead to improved backlog refinement, clearer priorities, and a more consistent flow of work for the development team. While discussing the issue with stakeholders is generally a good practice, providing training to the product owner is a more immediate and specific action to address the current problem of work flow in the agile project. "
upvoted 2 times
...
Fyrus
12 months ago
Selected Answer: D
After the sprint review. I would ask their opinion. Why should be the PO to get training? Is the team to define, together, what goes and what doesn't go in the sprint. The PO may be responsible for the backlog but this is it. May be the dev team to accept to much work... Talk with people, analyze and then act
upvoted 1 times
...
kayyaly
1 year ago
Selected Answer: D
D: need to discuss with stakeholders first
upvoted 1 times
...
victory108
1 year, 1 month ago
Selected Answer: A
A. Provide the product owner with training
upvoted 1 times
...
SteAle
1 year, 2 months ago
Selected Answer: D
It is one of the Scrum Master/Project Manager's responsibilities to streamline the work, not PO. I would discuss the issue with the team first. No one says that this discussion will happen with ALL the stakeholders, only the scrum team + PO.
upvoted 1 times
...
TBT_1
1 year, 3 months ago
Selected Answer: D
Since there is no flow, it means the issue is not with the backlog, it has no tasks that are being fed properly, so discussing them with stakeholders may help.
upvoted 1 times
...
emelba
1 year, 4 months ago
Selected Answer: D
D is correct. The problem identified does not suggest that a hybrid approach is required. Providing the product owner with training, might be a valid action in some cases, but in this situation, the problem identified is related to the flow of work for the team. Training the product owner alone may not directly address this issue. To address this issue effectively, it is crucial for the project manager to engage with the stakeholders, including the product owner, to discuss and identify potential solutions.
upvoted 2 times
...
AP2023S
1 year, 4 months ago
Selected Answer: A
So, since we have problems with PO not being able to properly feed the team through proper backlog management, then let's talk about this problem with ALL stakeholders which could be dozens and dozens!!! Yes.. of course...
upvoted 3 times
SteAle
1 year, 2 months ago
No one said ALL, read the answer carefully
upvoted 2 times
...
...
JYKL88
1 year, 4 months ago
i will go for D
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...