A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs.
What should the project manager do?
rajeshtk
Highly Voted 2 years, 7 months agodinodragon
10 months, 2 weeks agoBobbie30
2 years, 4 months agoljz
Most Recent 1 month, 2 weeks ago462729f
1 month, 3 weeks agoJordarlu
2 months, 1 week agoWWu
3 months, 1 week agoWWu
3 months, 1 week ago8d5c185
3 months, 1 week agoKim222
7 months, 2 weeks agoea4e1f8
7 months, 3 weeks agotonybuivannghia
8 months, 4 weeks agoMusaad
1 year, 2 months agoJaya12
1 year, 4 months agocertificate988
1 year, 4 months agocertificate988
1 year, 4 months agoreaganFF
1 year, 3 months agoOnly12go
1 year, 5 months agoDavid983
1 year, 6 months agovictory108
1 year, 7 months agoAish_
1 year, 8 months agoJamrock
1 year, 8 months agonemm235
1 year, 6 months ago