A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV) to actual cost (AC) for the project and has found the calculated result to be 0.9024.
What does this value mean for the project?
pmp_237student
Highly Voted 2 years, 3 months agoPrimacomSHU
1 year, 5 months agochxzqw
Highly Voted 2 years, 3 months agokavikris
Most Recent 4 months agoLotToLearn
6 months agodiegovcz
7 months, 3 weeks agodiegovcz
7 months, 3 weeks agoParamak
8 months, 2 weeks agotonybuivannghia
8 months, 2 weeks agonqbaotd
10 months agoakashushi007
10 months, 2 weeks agojiljap
11 months, 1 week agoMartinussantika
11 months, 3 weeks agoMartinussantika
2 months, 1 week agoAwaisalam
1 year agosegatarasov
1 year, 1 month agoodylec
1 year, 2 months agoodylec
1 year, 2 months agoleo9944
1 year, 2 months agoatoms101
1 year, 3 months ago