A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV) to actual cost (AC) for the project and has found the calculated result to be 0.9024.
What does this value mean for the project?
pmp_237student
Highly Voted 2 years, 3 months agoPrimacomSHU
1 year, 5 months agochxzqw
Highly Voted 2 years, 4 months agocloudreddy
Most Recent 2 weeks, 2 days agokavikris
4 months, 3 weeks agoLotToLearn
6 months, 4 weeks agodiegovcz
8 months, 2 weeks agodiegovcz
8 months, 2 weeks agoParamak
9 months, 1 week agotonybuivannghia
9 months, 1 week agonqbaotd
10 months, 3 weeks agoakashushi007
11 months, 1 week agojiljap
12 months agoMartinussantika
1 year agoMartinussantika
3 months agoAwaisalam
1 year agosegatarasov
1 year, 1 month agoodylec
1 year, 3 months agoodylec
1 year, 3 months agoleo9944
1 year, 3 months ago