A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV) to actual cost (AC) for the project and has found the calculated result to be 0.9024.
What does this value mean for the project?
pmp_237student
Highly Voted 1 year, 8 months agoPrimacomSHU
10 months, 3 weeks agochxzqw
Highly Voted 1 year, 9 months agodiegovcz
Most Recent 1 month, 2 weeks agodiegovcz
1 month, 2 weeks agoParamak
2 months agotonybuivannghia
2 months agonqbaotd
3 months, 2 weeks agoakashushi007
4 months, 1 week agojiljap
4 months, 4 weeks agoMartinussantika
5 months, 2 weeks agoAwaisalam
5 months, 3 weeks agosegatarasov
6 months, 4 weeks agoodylec
8 months agoodylec
8 months agoleo9944
8 months, 3 weeks agoatoms101
9 months agoBruce_Liu
9 months agoDeeski
9 months ago