A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV) to actual cost (AC) for the project and has found the calculated result to be 0.9024.
What does this value mean for the project?
pmp_237student
Highly Voted 1 year, 11 months agoPrimacomSHU
1 year agochxzqw
Highly Voted 1 year, 11 months agoLotToLearn
Most Recent 1 month, 4 weeks agodiegovcz
3 months, 2 weeks agodiegovcz
3 months, 2 weeks agoParamak
4 months, 1 week agotonybuivannghia
4 months, 1 week agonqbaotd
5 months, 3 weeks agoakashushi007
6 months, 1 week agojiljap
7 months agoMartinussantika
7 months, 2 weeks agoAwaisalam
7 months, 4 weeks agosegatarasov
9 months agoodylec
10 months, 1 week agoodylec
10 months, 1 week agoleo9944
10 months, 3 weeks agoatoms101
11 months agoBruce_Liu
11 months ago