An agile team is working on a 2-week sprint to deliver business value. About 1 week after the sprint starts, the team members do not feel confident about the product increment they are building. They do not want to wait until the end of the sprint and want to validate the product increment with the product owner now.
What should the project manager do to mitigate this risk?
Adeshola1960
Highly Voted 1 year, 10 months agoQuaTV
Most Recent 2 months, 1 week agoParamak
4 months, 1 week agomdkhassan
8 months agojosephsafiran
10 months, 3 weeks agoBruce_Liu
11 months agoDeeski
11 months, 1 week agoChezQW
1 year, 1 month agoLucky_Cindy
1 year, 1 month agoLucky_Cindy
1 year, 1 month agoOnly12go
1 year, 1 month agobu02951
1 year, 1 month agoTuanit
1 year, 1 month agozayn_1983
1 year, 3 months agoFyrus
1 year, 2 months agovictory108
1 year, 3 months agoMuntadher
1 year, 4 months agoAbbasTaki
1 year, 5 months ago