Question #: 622
Topic #: 1
[All PMP Questions]

A project manager is initiating an agile project for which some external components will be delivered by vendors. One of the vendors, however, will be unable to deliver its component in an incremental, collaborative way.
How should the project manager handle this situation?

  • A. Submit a request to the project sponsor to have the vendor replaced with a vendor who can work following an agile approach.
  • B. Ask the project management office (PMO) to abandon using an agile approach on the project to accommodate the vendor.
  • C. Have the vendor deliver the component using another approach, then integrate it into the project without changing the overall agile approach.
  • D. Ask the product owner to move the component to the product backlog to be addressed after the work using an agile approach has been completed.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Paramak
4 weeks, 1 day ago
Selected Answer: C
Most of these Examtopic answers are incorrect.
upvoted 2 times
...
Abdelmonm
7 months, 3 weeks ago
Selected Answer: C
In agile projects, it's important to be flexible and adapt to the specific circumstances of the project. If a vendor is unable to deliver components in an incremental, collaborative way, the project manager can allow the vendor to use an alternative approach, such as a traditional delivery method. The key is to find a solution that allows the project to proceed while accommodating the constraints or limitations of external contributors. Integrating the vendor's components into the overall project can still follow agile principles, even if the vendor's delivery method differs.
upvoted 2 times
...
chlaithem
8 months, 2 weeks ago
Selected Answer: C
This option offers several advantages: Preserves agile benefits: Maintaining the overall agile approach ensures the project continues to leverage its advantages, such as iterative development, continuous feedback, and adaptability. Accommodates vendor limitations: Adapting to the vendor's delivery method demonstrates flexibility and avoids unnecessary disruptions by seeking a replacement or abandoning the agile approach entirely. Integrative solution: By planning for seamless integration of the vendor's component, the project can still achieve its overall goals without compromising the agile flow.
upvoted 2 times
...
UppersquareCapital
8 months, 3 weeks ago
Selected Answer: C
Option C provides a pragmatic approach by having the vendor deliver the component using their preferred approach and then integrating it into the agile project without changing the overall agile methodology. This allows the project to continue following agile principles while accommodating the specific situation with the vendor.
upvoted 3 times
...
victory108
12 months ago
Selected Answer: C
C. Have the vendor deliver the component using another approach, then integrate it into the project without changing the overall agile approach
upvoted 2 times
...
Aish_
1 year, 1 month ago
Selected Answer: C
By choosing option C, the project manager maintains the benefits of the agile approach for the project while accommodating the specific situation with the vendor. This approach allows the project to continue with its agile practices for other components while efficiently incorporating the vendor's deliverable using a different approach. It ensures the project stays on track while still fulfilling the contractual requirements with the vendor.
upvoted 2 times
...
smartrammy
1 year, 2 months ago
Selected Answer: C
The project manager should handle this situation by having the vendor deliver the component using another approach, then integrate it into the project without changing the overall agile approach.
upvoted 1 times
...
AstridN
1 year, 2 months ago
Was on C.. The frustrating part is not having an explanation..
upvoted 2 times
...
emelba
1 year, 4 months ago
Selected Answer: C
IA says: Option B, asking the project management office (PMO) to abandon using an agile approach to accommodate the vendor, is not recommended. It is important to maintain consistency in project management methodologies and not compromise the entire project's approach for one vendor. It is more practical to find a way to integrate the vendor's component within the existing agile framework. Therefore, option C is the most appropriate choice. The project manager should work with the vendor to find an alternative approach for delivering the component that aligns with the overall agile approach of the project.
upvoted 2 times
...
RevZig67
1 year, 5 months ago
Selected Answer: C
The agile approach emphasizes incremental and collaborative delivery of the product, so if a vendor cannot deliver their component in this way, the project manager can work with the vendor to come up with a different approach that still meets the project requirements. The project manager can then integrate the component into the project without changing the overall agile approach. This allows the project to continue to follow agile principles while still accommodating the vendor's limitations.
upvoted 2 times
...
Weslineo
1 year, 7 months ago
We cannot abandon a project methodology chosen because of one vendor,rather we should try to accommodate the one vendor by going hybrid.C is correct
upvoted 2 times
...
mjs
1 year, 9 months ago
Selected Answer: C
C is the best answer
upvoted 2 times
...
leo_gold
1 year, 9 months ago
Selected Answer: C
C is the best answer within whats provided
upvoted 1 times
...
SASA2030
1 year, 9 months ago
I will go with C
upvoted 1 times
...
15rajanikanthhotie
1 year, 9 months ago
Why not A is answer?
upvoted 1 times
...
Bobbie30
1 year, 9 months ago
I'll go with C
upvoted 1 times
...
vkgdasa
1 year, 10 months ago
Selected Answer: C
Seems like hybrid to me
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...