A project manager is leading a meeting with key stakeholders, the project sponsor and the product owner to define the features that will be released after the next iteration. The purpose of the meeting is to review the product backlog prioritization, considering that during the past iteration some deliverables were not completed.
Which two items should be taken into account first to review and update the product backlog priorities during the meeting? (Choose two.)
YSO34
Highly Voted 2 years ago[Removed]
1 year, 11 months agorajeshtk
1 year, 11 months agoPMPStudent
Highly Voted 1 year, 9 months agoKim222
Most Recent 3 weeks agoxcjxcj
8 months, 4 weeks agoSumbo
11 months, 2 weeks agovictory108
1 year agoHung1
1 year, 5 months ago