A team working on a close deployment waits to receive critical information from the customer. The customer keeps postponing sending the information which is delaying the deployment. What should the project manager have done to prevent the delay?
A.
Obtained all critical information ahead of time
B.
Involved the customer in the deployment process
yes, talking with people and explaining a situation and exchanging expectations creates a feeling of appreciation and mutual trust which helps to avoid these situations in most of the cases!
When a project is delayed due to a customer’s inability to provide critical information, the project manager should take proactive measures to minimize the impact of the delay. One of the most effective ways to do this is to involve the customer in the deployment process 1. This will help ensure that the customer is aware of the importance of providing the necessary information and is committed to doing so in a timely manner.
Obtaining all critical information ahead of time (option A) is not always feasible, especially if the information is not yet available or if it is subject to change.
A: also, it is mentioned the project is close to deployment, so that means the customer was involved in other points of the project, just not the last one. So PM must work on it.
The team is trying to involve the customer but the customer is not collaborating, so the PM must meet with the customer when he or she has time to obtain the info ahead of deployment. We have an issue of communication, so the PM must tailor communications to fit the stakeholder.
This is the response I got from Chat GPT - While involving the customer in the deployment process (option B) and involving upper management (option D) are also important, they are more reactive measures. Using sample data (option C) might be a temporary workaround but doesn't address the root cause of the delay. Obtaining all critical information ahead of time (option A) is a proactive and strategic approach that effectively prevents such delays.
A: is the right answer. As a developer, usually you do not involve the customer in deployment process. As they do not understand the technical work. So given the scenario, A would be a preferred choice
According to PMI best practices, the most appropriate action to prevent the delay would be:
A. Obtained all critical information ahead of time
This option aligns with proactive project management principles. By obtaining all critical information in advance, the project manager can mitigate the risk of delays caused by waiting for customer inputs. This ensures that the project has the necessary data to proceed without interruptions, reflecting good planning and risk management.
According to the PMBOK Guide, the correct answer that aligns with PMI's recommended practices is A. Obtained all critical information ahead of time.
Option B is not correct because involvement of the the customer is too late.....
however the question is: What should the project manager have done to prevent the delay? have done are the key words in this case, not what should the PM will do or needs to do next...
A, because Client already put you down from the priority list, useless to get more touch base with them since they may need time to general data as well or jump into other staff, should make more effort from the team itself which is do more planning/get more data ahead.
The given answer is absolutely correct. Not all critical information will be obtained in the early stages of the project. New and emerging variables will come during execution that will also be critical to the project and they won't be obtained in the early stages. So the best to do is to involve the customer in the process from the onset. This makes the customer part of the process and sure costumer buy-in throughout. B is the correct answer as it's impractical to obtain all critical information ahead of time.
I am having a hard time with this one, I selected A as correct. Wouldn't having all the information in the beginning prevent any delays? Even if there was involvement with the customer, there is still risk for the customer to delay providing information. The question doesn't specify the cause for delay, but having the information in the beginning would prevent this issue.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Erpy
Highly Voted 2 years, 2 months agoarnibert
2 years, 1 month agommhawish
Highly Voted 11 months, 3 weeks agokavikris
Most Recent 3 weeks, 4 days agocrypto_dreams_medellin
1 month, 2 weeks agocrypto_dreams_medellin
1 month, 2 weeks agoPhongDang_PM
1 month, 2 weeks ago098575305
5 months, 3 weeks agoShivYad
6 months, 2 weeks agoAustinIgnatius
6 months, 3 weeks agoyassinehelp
6 months, 3 weeks ago52d1fe0
7 months, 4 weeks agoKaran1102
8 months, 2 weeks agodiegovcz
6 months, 3 weeks agonichwc
10 months, 3 weeks agoBuviD
11 months, 3 weeks agoGabMonterey
1 year agovatsan1980
1 year, 1 month agoHashi1_snr
1 year, 2 months agodjgdgaf
10 months ago