exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 29 discussion

Actual exam question from PMI's PMP
Question #: 29
Topic #: 1
[All PMP Questions]

A team working on a close deployment waits to receive critical information from the customer. The customer keeps postponing sending the information which is delaying the deployment.
What should the project manager have done to prevent the delay?

  • A. Obtained all critical information ahead of time
  • B. Involved the customer in the deployment process
  • C. Used the sample data already in place
  • D. Involved upper management in the process
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Erpy
Highly Voted 2 years, 6 months ago
B - because it the answer that involves collaboration. Also, involvement allows progressive elaboration.
upvoted 17 times
arnibert
2 years, 5 months ago
yes, talking with people and explaining a situation and exchanging expectations creates a feeling of appreciation and mutual trust which helps to avoid these situations in most of the cases!
upvoted 2 times
...
...
mmhawish
Highly Voted 1 year, 3 months ago
Selected Answer: B
When a project is delayed due to a customer’s inability to provide critical information, the project manager should take proactive measures to minimize the impact of the delay. One of the most effective ways to do this is to involve the customer in the deployment process 1. This will help ensure that the customer is aware of the importance of providing the necessary information and is committed to doing so in a timely manner. Obtaining all critical information ahead of time (option A) is not always feasible, especially if the information is not yet available or if it is subject to change.
upvoted 8 times
...
Princessviv96
Most Recent 3 days, 9 hours ago
Selected Answer: A
Its important that the project manager should collect all the important and vital information from the client early before starting the project during the requirement gathering phase, this will reduce instances of having to be stuck when the client does not respond on time thereby halting the project progress.
upvoted 1 times
...
ductrinh
1 week, 5 days ago
Selected Answer: B
b is the best choice
upvoted 1 times
...
maya1
1 week, 6 days ago
Selected Answer: A
Most reasonable explanation shared in the comments.
upvoted 1 times
...
shpunk
1 month, 3 weeks ago
Selected Answer: A
the customer already IS involved, they're just milking it. The correct answer is A.
upvoted 1 times
...
wisegik
2 months, 3 weeks ago
Selected Answer: A
The question says "The customer keeps postposing sending the information which is delaying deployment", I don't think option B is correct because if the customer keeps postposing sending an information, how will the PM get that customer in the deployment process
upvoted 1 times
...
K91
3 months ago
Selected Answer: B
My answer is B. A may not be possible, so making the customer responsible is more important, which is B.
upvoted 1 times
...
kavikris
4 months ago
Selected Answer: B
Involving the customer makes it collaborative and proactive
upvoted 1 times
...
crypto_dreams_medellin
4 months, 3 weeks ago
A: also, it is mentioned the project is close to deployment, so that means the customer was involved in other points of the project, just not the last one. So PM must work on it.
upvoted 1 times
...
crypto_dreams_medellin
4 months, 3 weeks ago
The team is trying to involve the customer but the customer is not collaborating, so the PM must meet with the customer when he or she has time to obtain the info ahead of deployment. We have an issue of communication, so the PM must tailor communications to fit the stakeholder.
upvoted 1 times
...
PhongDang_PM
5 months ago
B Since "the customer keeps postponing sending information", involve them in the deployment process should be the best choice
upvoted 1 times
...
098575305
9 months, 1 week ago
I think it should be A
upvoted 2 times
...
ShivYad
9 months, 3 weeks ago
Selected Answer: A
This is the response I got from Chat GPT - While involving the customer in the deployment process (option B) and involving upper management (option D) are also important, they are more reactive measures. Using sample data (option C) might be a temporary workaround but doesn't address the root cause of the delay. Obtaining all critical information ahead of time (option A) is a proactive and strategic approach that effectively prevents such delays.
upvoted 7 times
...
AustinIgnatius
10 months ago
A: is the right answer. As a developer, usually you do not involve the customer in deployment process. As they do not understand the technical work. So given the scenario, A would be a preferred choice
upvoted 4 times
...
yassinehelp
10 months ago
According to PMI best practices, the most appropriate action to prevent the delay would be: A. Obtained all critical information ahead of time This option aligns with proactive project management principles. By obtaining all critical information in advance, the project manager can mitigate the risk of delays caused by waiting for customer inputs. This ensures that the project has the necessary data to proceed without interruptions, reflecting good planning and risk management.
upvoted 1 times
...
52d1fe0
11 months, 1 week ago
Selected Answer: B
collaboration with customer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago