Team A is working on the second sprint of a product release. Team B, which is an interdependent team located on the same floor, requires exclusive and frequent information to complete its sprint goal. What should the agile team do?
A.
Create a central repository for information, and provide access to team B
B.
Use an information board that will be visible to all passing through the workspace
C.
Email all stakeholders with status updates
D.
Provide team B with the information on an ג€as neededג€ basis
B = correct
According to Agile, the team has to promote transparency by using information radiators. In this case, the A & B teams are on the same floor and logically, an info board could improve the transparency among the teams.
Option B.
Agile methodology emphasizes visual communication and information radiators to promote transparency and collaboration among team members. Using an information board that is visible to all team members passing through the workspace can help provide exclusive and frequent information to Team B. This can help promote transparency and facilitate communication between the teams, enabling them to work collaboratively and efficiently. Additionally, it can help reduce the need for additional communication channels such as email, which can be time-consuming and may not be as effective in promoting collaboration.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
sleekygurl
1 month, 2 weeks agofkr
6 months agoPetrevski
1 year, 7 months agoSmokeyofficiial
1 year, 8 months agoInvisibleBeing
1 year, 10 months agoGrandMasta
2 years, 2 months agominwang
2 years, 2 months agominwang
2 years, 2 months ago