A building management system (BMS) project is in its commissioning phase and handover to the operations team will commence soon. However, the project manager noted that both the project and operation teams are not able to properly operate the BMS. As a result, there is an increased risk of the project schedule being delayed.
What should the project manager have done to avoid this situation?
[Removed]
Highly Voted 2 years, 6 months agorajeshtk
2 years, 6 months agoarnibert
2 years, 5 months agoPMPStudent69
2 years, 2 months agolilylam08
2 years agoPrincessviv96
Most Recent 3 days, 9 hours agoductrinh
1 week, 5 days agoK91
3 months agoLifestrongK
4 months agocrypto_dreams_medellin
4 months, 3 weeks agoCaesar88
11 months, 4 weeks agoBuviD
1 year, 3 months agoGabMonterey
1 year, 4 months agoAish_
1 year, 8 months agoMuntadher
1 year, 8 months agovictory108
1 year, 11 months agoBenPappoe
1 year, 11 months agoAnna12675
1 year, 11 months agowzjh2008
2 years agoLeylae
2 years agoBakM
1 year, 6 months agoGanzee
2 years, 3 months agoguyver0523
2 years, 7 months ago