A building management system (BMS) project is in its commissioning phase and handover to the operations team will commence soon. However, the project manager noted that both the project and operation teams are not able to properly operate the BMS. As a result, there is an increased risk of the project schedule being delayed.
What should the project manager have done to avoid this situation?
[Removed]
Highly Voted 2 years, 3 months agorajeshtk
2 years, 3 months agoarnibert
2 years, 1 month agoPMPStudent69
1 year, 11 months agolilylam08
1 year, 9 months agoLifestrongK
Most Recent 2 weeks, 6 days agocrypto_dreams_medellin
1 month, 2 weeks agoCaesar88
8 months, 2 weeks agoBuviD
11 months, 3 weeks agoGabMonterey
1 year agoAish_
1 year, 4 months agoMuntadher
1 year, 5 months agovictory108
1 year, 7 months agoBenPappoe
1 year, 8 months agoAnna12675
1 year, 8 months agowzjh2008
1 year, 9 months agoLeylae
1 year, 9 months agoBakM
1 year, 2 months agoGanzee
2 years agoguyver0523
2 years, 3 months ago