Question #: 21
Topic #: 1
[All PMP Questions]

During the lessons learned workshop, one stakeholder mentioned that the project was unsuccessful as it did not deliver the expected business value.
What should the project manager do to address this concern?

  • A. Review the project management plan tasks with the stakeholders.
  • B. Review the business benefits realization plan with the stakeholders.
  • C. Review the project management plan budget with the stakeholders.
  • D. Review the communications management plan with the stakeholders.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Deepakuc
1 week, 4 days ago
Option B
upvoted 1 times
...
053e3de
5 months, 3 weeks ago
I chose B because the question was talking about business value. Another word for "benefits" that can come out of the project.
upvoted 2 times
...
BuviD
10 months, 3 weeks ago
Selected Answer: A
A. Review the project management plan tasks with the stakeholders.
upvoted 1 times
...
Kalhan06
11 months, 3 weeks ago
Selected Answer: B
B is correct.
upvoted 1 times
...
Tuanit
1 year, 1 month ago
Selected Answer: B
B is correct. Projects may perfectly follow schedule, fulfill requirement and meet quality but still can't achieve desired benefit.
upvoted 2 times
...
Lucky_Cindy
1 year, 2 months ago
B is correct
upvoted 1 times
...
Remmy12
1 year, 2 months ago
B. Review the plan with the Stakeholders.
upvoted 1 times
...
Desmonddoyin
1 year, 4 months ago
Selected Answer: B
Reviewing the business benefit plan can help to determine if the project objectives has been met
upvoted 1 times
...
victory108
1 year, 6 months ago
Selected Answer: B
B. Review the business benefits realization plan with the stakeholders
upvoted 1 times
...
BenPappoe
1 year, 7 months ago
Selected Answer: B
Voted B
upvoted 1 times
...
Rena1352
1 year, 7 months ago
B is correct
upvoted 1 times
...
JRC83
1 year, 7 months ago
Selected Answer: B
I think it is B, answer is found on p.187 of PMBOK 7th ed.
upvoted 2 times
...
Anna12675
1 year, 7 months ago
Selected Answer: B
B IS CORRECT
upvoted 1 times
...
Anna12675
1 year, 7 months ago
Selected Answer: A
A OR D
upvoted 1 times
...
Ganzee
1 year, 11 months ago
C. Review the project management plan budget with the stakeholders.
upvoted 1 times
...
MrCorc
2 years, 2 months ago
there is no business benefits realization plan in pmbok!
upvoted 2 times
rajeshtk
2 years, 2 months ago
neither the business value specified in project management plan
upvoted 1 times
...
Nmeli
2 years, 1 month ago
pmbok 7th ed. pg.187.
upvoted 9 times
thetailwind
2 years, 1 month ago
"BENEFITS REALIZATION PLAN: A document outlining the activities necessary for achieving the planned benefits. It identifies a timeline and the tools and resources necessary to ensure the benefits are fully realized over time...."
upvoted 11 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...