During the lessons learned workshop, one stakeholder mentioned that the project was unsuccessful as it did not deliver the expected business value. What should the project manager do to address this concern?
A.
Review the project management plan tasks with the stakeholders.
B.
Review the business benefits realization plan with the stakeholders.
C.
Review the project management plan budget with the stakeholders.
D.
Review the communications management plan with the stakeholders.
"BENEFITS REALIZATION PLAN: A document outlining the activities necessary for achieving the planned benefits. It identifies a
timeline and the tools and resources necessary to ensure the benefits are fully realized over time...."
upvoted 11 times
...
...
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Deepakuc
1 week, 4 days ago053e3de
5 months, 3 weeks agoBuviD
10 months, 3 weeks agoKalhan06
11 months, 3 weeks agoTuanit
1 year, 1 month agoLucky_Cindy
1 year, 2 months agoRemmy12
1 year, 2 months agoDesmonddoyin
1 year, 4 months agovictory108
1 year, 6 months agoBenPappoe
1 year, 7 months agoRena1352
1 year, 7 months agoJRC83
1 year, 7 months agoAnna12675
1 year, 7 months agoAnna12675
1 year, 7 months agoGanzee
1 year, 11 months agoMrCorc
2 years, 2 months agorajeshtk
2 years, 2 months agoNmeli
2 years, 1 month agothetailwind
2 years, 1 month ago