A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.
What should the project manager do next?
Hao2
Highly Voted 7 months agoAcumen88
1 year, 10 months agoSaadalfehri
Most Recent 2 days, 15 hours agobetterthanyesterday
2 days, 17 hours agoHubertP
4 days, 12 hours agoJAQM
1 week, 2 days agoPrincessviv96
1 week, 4 days agojamese_clarke
3 weeks, 5 days ago19d3b19
1 month agovanwanpmp
2 months agoengamin
2 months, 1 week agoTerryV01
2 months, 1 week agoSMUNENE
3 months agoEZbaba101
3 months, 2 weeks agoFauziYusmin
3 months, 2 weeks agottkong168
4 months, 1 week agoMalikSaab
4 months, 2 weeks agoMrKee
4 months, 2 weeks ago