A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.
What should the project manager do next?
Hao2
Highly Voted 2 months agoAcumen88
1 year, 5 months agomuze1003
Most Recent 1 day, 9 hours agoDeepakuc
1 week, 4 days agoPragati06
2 months agoTaha1981
2 months agoPraveen13
2 months, 1 week agotelocop745
2 months, 2 weeks agokowab
3 months agohatanaoki
5 months, 3 weeks agoAditech
7 months, 2 weeks agoAnh_123
7 months, 2 weeks agoAlonsochaves
7 months, 3 weeks agoDMHR
10 months, 1 week agoBuviD
10 months, 3 weeks agovshreevj13
1 year, 1 month agoRavi4french
1 year, 1 month agoRaymond1105
1 year, 2 months ago