A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.
What should the project manager do next?
Hao2
Highly Voted 6 months, 1 week agoAcumen88
1 year, 9 months agojamese_clarke
Most Recent 5 days, 13 hours ago19d3b19
2 weeks, 1 day agovanwanpmp
1 month, 1 week agoengamin
1 month, 2 weeks agoTerryV01
1 month, 3 weeks agoSMUNENE
2 months, 1 week agoEZbaba101
2 months, 3 weeks agoFauziYusmin
2 months, 4 weeks agottkong168
3 months, 3 weeks agoMalikSaab
3 months, 3 weeks agoMrKee
3 months, 3 weeks agomahafido
4 months agoJoJaRa
4 months agomuze1003
4 months, 1 week agoDeepakuc
4 months, 2 weeks agoPragati06
6 months, 1 week ago