exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1 discussion

Actual exam question from PMI's PMP
Question #: 1
Topic #: 1
[All PMP Questions]

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.
What should the project manager do next?

  • A. Consult the risk register for an appropriate planned risk response and implement.
  • B. Revise the project management plan and move the task to a time when the technical resource will be available.
  • C. Review the business requirement with stakeholders and exclude the task assigned to the technical resource.
  • D. Update the lessons learned report and the risk log to reflect that this risk has materialized.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Hao2
Highly Voted 7 months ago
Selected Answer: A
Hint is PM already identified this risk during Project Planning. Output of Identify Risk process is Risk register. Basically, a good PM w/ 4 values & 12 principles under PMI languages need to do this task with due diligent thus Risk register can be used later as sufficient reference regarding risk response plan when relevant risk happen. A is still the correct answer.
upvoted 26 times
Acumen88
1 year, 10 months ago
Considering that the risk has been identified during project planning, the PM needs to consult the risk register to ascertain if there is a response to this risk. The answer is A.
upvoted 3 times
...
...
Saadalfehri
Most Recent 2 days, 15 hours ago
Selected Answer: A
A is the right answer since it's identified before.
upvoted 1 times
...
betterthanyesterday
2 days, 17 hours ago
Selected Answer: B
Why is B not correct?
upvoted 1 times
...
HubertP
4 days, 12 hours ago
Selected Answer: A
A is my answer
upvoted 1 times
...
JAQM
1 week, 2 days ago
Selected Answer: D
No estoy de acuerdo con la respuestas brindandas, teniendo en cuenta que proyecto siempre debe trabajar con su tema de Backup donde la operación conozca las diferentes situaciones del proyecto y cualquier persona deberia asumir la reponsabilidad para ejecutar los diferentes compromisos con el fin de garantizar una operación estable, dependiente de que las personas tengan situaciones dificiles siempre hay que verificar previamente como poder ayudar antes de que el riesgo de materialice.
upvoted 1 times
...
Princessviv96
1 week, 4 days ago
Selected Answer: A
A is the right point of action, consult the risk register for the appropriate risk to implement
upvoted 1 times
...
jamese_clarke
3 weeks, 5 days ago
Selected Answer: A
A, since the PM has already identified risk and response https://ln.run/VNr1a
upvoted 1 times
...
19d3b19
1 month ago
Selected Answer: A
Option A should be the correct answer
upvoted 1 times
...
vanwanpmp
2 months ago
Selected Answer: A
PM identified the risk in planning stage. The risk should be registered in risk registry as reference.
upvoted 1 times
...
engamin
2 months, 1 week ago
Selected Answer: A
A correct answer
upvoted 1 times
...
TerryV01
2 months, 1 week ago
Selected Answer: A
A, since the PM has already identified risk and response
upvoted 1 times
...
SMUNENE
3 months ago
Selected Answer: A
A . As PM you have already developed a risk register with various mitigation plans .Therefore once a risk occurs it is now an issue which requires to be addressed as per the plan
upvoted 1 times
...
EZbaba101
3 months, 2 weeks ago
Selected Answer: A
The key word is risk register
upvoted 1 times
...
FauziYusmin
3 months, 2 weeks ago
Selected Answer: A
he project manager should assess the impact on the critical path, attempt to reassign the task to another resource, adjust the schedule if necessary, communicate with stakeholders, and implement any pre-established risk mitigation strategies. Prompt action and effective communication are key to minimizing the disruption and keeping the project on track.
upvoted 1 times
...
ttkong168
4 months, 1 week ago
Selected Answer: A
PM should have plan the risk response during planning stage.
upvoted 1 times
...
MalikSaab
4 months, 2 weeks ago
Selected Answer: A
A is more relevant answer
upvoted 1 times
...
MrKee
4 months, 2 weeks ago
Selected Answer: A
Option A
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago