A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.
What should the project manager do next?
Hao2
Highly Voted 9 months, 2 weeks agoAcumen88
2 years agoyusuf452
Most Recent 4 days, 17 hours agoWakatobi
1 week, 6 days agosdbol
4 weeks agoArthsath
1 month, 1 week agoMTK17
1 month, 2 weeks agoSaadalfehri
2 months, 2 weeks agobetterthanyesterday
2 months, 2 weeks agoHubertP
2 months, 2 weeks agoJAQM
2 months, 3 weeks agoPrincessviv96
2 months, 3 weeks ago19d3b19
3 months, 3 weeks agovanwanpmp
4 months, 2 weeks agoengamin
4 months, 3 weeks agoTerryV01
4 months, 3 weeks agoSMUNENE
5 months, 2 weeks agoEZbaba101
6 months ago