A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.
What should the project manager do next?
Hao2
Highly Voted 3 months agoAcumen88
1 year, 6 months agorajetaf
Highly Voted 1 week, 5 days agottkong168
Most Recent 1 week, 6 days agoMalikSaab
2 weeks, 5 days agoMrKee
2 weeks, 5 days agomahafido
3 weeks, 2 days agoJoJaRa
3 weeks, 5 days agomuze1003
1 month agoDeepakuc
1 month, 1 week agoPragati06
3 months agoTaha1981
3 months agoPraveen13
3 months, 1 week agotelocop745
3 months, 2 weeks agokowab
4 months agohatanaoki
6 months, 3 weeks agoAditech
8 months, 2 weeks agoAnh_123
8 months, 2 weeks ago