Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 31 discussion

Actual exam question from PMI's PMI-ACP
Question #: 31
Topic #: 1
[All PMI-ACP Questions]

When prioritizing features to be delivered in an iteration, on what should an agile team defer work?

  • A. High-risk and high-value
  • B. High-risk and low-value
  • C. Low-risk and low-value
  • D. Low-risk and high value
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
thewalker
3 weeks, 4 days ago
Selected Answer: C
When prioritizing features to be delivered in an iteration, an agile team should defer work on low-risk and low-value items. This approach ensures that the team focuses on delivering the most valuable and impactful features first, while minimizing risk.
upvoted 1 times
...
zayn_1983
2 months, 1 week ago
High value and high risk features should be prioritized, then high-value low-risk, finally low-value and low-risk.
upvoted 1 times
...
HenryBach
6 months, 4 weeks ago
Selected Answer: B
B is correct
upvoted 1 times
...
195daa8
7 months ago
Option B aligns with Lean principles, specifically the concept of value stream mapping, which is used to visualize the steps involved in delivering value to the customer and identify opportunities for improvement. By reviewing the process value stream, the agile team can analyze the efficiency of the current process activities and identify areas where improvements can be made to enhance efficiency and effectiveness.
upvoted 1 times
...
Michaela0015
8 months, 1 week ago
Selected Answer: B
B is correct. "Defer work on all low-value features, especially those that are also high risk." https://www.linkedin.com/pulse/agile-planning-prioritization-desirability-borjan-petreski
upvoted 2 times
ELTIGANI
2 months, 1 week ago
The shared article confirms that C is the correct answer (Low-Value & Low-Risk items should be delayed).
upvoted 1 times
...
...
Nervys
8 months, 4 weeks ago
Selected Answer: B
B for sure
upvoted 2 times
...
itsmewajid
9 months, 2 weeks ago
Selected Answer: C
High Risk High value can't be deffered.
upvoted 1 times
...
Imrangoshi
1 year ago
Selected Answer: C
high risk means, making mistakes and learning if there is any challenge in it.
upvoted 1 times
ImGonnaPassIt
5 months, 3 weeks ago
High-risk and low-value features present a high potential cost in terms of risk without a corresponding high level of benefit, making them a lower priority compared to features that either offer higher value or come with lower risk. Prioritizing high-value work that aligns with the product vision and customer needs is key in Agile development, while risks should be managed strategically.
upvoted 1 times
...
...
Imrangoshi
1 year ago
Selected Answer: C
C is the Correct Answer
upvoted 1 times
...
NorWEED
1 year, 2 months ago
B. High-risk and low-value. Explanation: The goal in Agile is to deliver the most valuable features as early as possible and to tackle risks while doing so. Thus, features that are high-risk and high-value should not be deferred but tackled head-on. On the contrary, features that are high-risk and low-value don't provide enough value to justify the associated risk, so these should be deferred or even avoided. Low-risk and high-value features (Option D) are desirable as they give the team valuable output with minimal risk. Low-risk and low-value features (Option C) could be deferred or might be tackled as time and resources allow, but they wouldn't be a first priority. Remember, the goal is to provide the maximum value with minimal risk, and the team should focus on high-value work first. The risk is considered to ensure that potential problems are dealt with sooner rather than later.
upvoted 2 times
...
abhi517
1 year, 5 months ago
Selected Answer: C
When prioritizing features to be delivered in an iteration, an agile team should defer work on low-risk and low-value features. Therefore, the correct option is C. Low-risk and low-value. Agile teams should prioritize high-risk and high-value features to be delivered first, followed by low-risk and high-value features. Low-risk and low-value features should be considered for deferral to future iterations, as they are not critical to the success of the project and can be postponed to focus on more important items.
upvoted 3 times
Agile_Dario_Conde
1 year, 3 months ago
I agree
upvoted 1 times
...
...
Petrevski
1 year, 5 months ago
Selected Answer: B
A = high priority - do first B = low priority - avoid / defer (correct) C = medium priority - do last D = medium priority - do second
upvoted 2 times
...
tuanphongpro123
1 year, 7 months ago
C is correct. https://university.hygger.io/en/articles/2399041-value-vs-risk-model
upvoted 2 times
...
Holly2023
1 year, 7 months ago
Selected Answer: C
C, low risk & low value = do last ==> defer It's not B because high risk & low value = avoid
upvoted 2 times
Notmeforsure
6 months, 2 weeks ago
I think this answer makes more sense
upvoted 1 times
...
...
InvisibleBeing
1 year, 8 months ago
Selected Answer: B
I believe the correct answer is B. The item with the lowest value and high-risk is the worst in the product backlog. What it means is that there are many risks involved with the item, but the value earned is very little. It is not worth the risk, where value driven is less than what it costs to mitigate risks.
upvoted 1 times
...
Nhuho
1 year, 8 months ago
Selected Answer: B
B High-risk and low-value
upvoted 1 times
...
Chikhalsouk
1 year, 10 months ago
High-risk and low-value
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...