Question #: 538
Topic #: 1
[All PMP Questions]

A project manager for a maintenance project has a contract that is renewed annually. The project started 6 years ago. After contract renewal this year the auditors reported that this version of the contract violates a new law that was passed last year.
What has happened in this situation?

  • A. The contract has not been appropriately reviewed by the project team
  • B. The stakeholder engagement plan has not been correctly implemented
  • C. The legal department has not disseminated the law correctly to all staff
  • D. The project manager does not have enough knowledge on this legal matter
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
3 weeks ago
Selected Answer: A
Isn't it the team's job to manage contracts? It is possible that the legal team will not know the details of the contract without the team's request. The team is well aware of the current contract details. The PM should have proactively worked with the legal team when reviewing the contract.
upvoted 1 times
...
tonybuivannghia
1 month, 4 weeks ago
Selected Answer: C
In this scenario, the auditors have identified that the current version of the contract violates a new law that was passed last year. This indicates that the project team was not aware of this new law or its implications when renewing the contract this year. The responsibility for disseminating legal updates and ensuring compliance typically falls under the legal department's domain within an organization. Therefore, the issue lies in the legal department not effectively communicating or disseminating the new law to all relevant staff, including the project team responsible for contract renewal
upvoted 2 times
...
josephsafiran
7 months, 3 weeks ago
Selected Answer: A
The situation described indicates that **A. The contract has not been appropriately reviewed by the project team**. When a contract is renewed, it should be reviewed to ensure that it complies with all current laws and regulations. In this case, a new law was passed last year, but the renewed contract violates this law. This suggests that the project team did not properly review the contract in light of the new law before renewing it. It's important for project teams to stay up-to-date with relevant laws and regulations to avoid such issues.
upvoted 2 times
dinodragon
3 months, 2 weeks ago
Have not seen project teams reviewing contracts ever for any maintenance projects. Responsibility of project manager and stakeholders. So, my guess is B. Not C because Legal department can never realistically keep on passing new rules to all staff.
upvoted 1 times
...
...
Delab202
8 months ago
Selected Answer: C
C. The legal department has not disseminated the law correctly to all staff. Here's why: A. Contract not reviewed by project team: While the project team might not have reviewed the contract in detail, it's more likely that a legal violation, especially something as blatant as a new law, would have been flagged by legal professionals. B. Stakeholder engagement plan not implemented: A stakeholder engagement plan typically focuses on communication and collaboration, not legal compliance. This wouldn't directly explain the contract violation. D. Project manager lacks legal knowledge: While project managers don't need to be legal experts, they often rely on internal legal resources like the legal department for guidance. Assuming they consulted with legal, the responsibility for dissemination likely lies with that department.
upvoted 1 times
...
certificate988
9 months, 3 weeks ago
Selected Answer: B
Law is passed last year...project team may not be aware of the law until communicated by legal team which can happen only when stakeholder engagement plan is implemented correctly to engage with legal team. So, best option is B.
upvoted 3 times
...
David983
11 months ago
Selected Answer: B
Agree with SteAle: Selected Answer: B The legal Department is an important stakeholder and should have been engaged in the project
upvoted 1 times
...
Only12go
11 months ago
Selected Answer: A
The scenario states that the project's contract is renewed annually and that the latest version of the contract violates a new law passed the previous year. This indicates that when the contract was renewed this year, it wasn't thoroughly reviewed or updated to ensure compliance with the new law.
upvoted 2 times
...
victory108
1 year ago
Selected Answer: A
A. The contract has not been appropriately reviewed by the project team
upvoted 1 times
...
SynikalDemon
1 year, 2 months ago
A or B are the only real answers, and A seems best.
upvoted 1 times
...
SteAle
1 year, 2 months ago
Selected Answer: B
The legal Department is an important stakeholder and should have been engaged in the project
upvoted 3 times
...
kevzzz
1 year, 2 months ago
Selected Answer: A
Complacency on the part of the project team since the project has been going for 6 years. The project team needs to properly review each contract and check for applicable laws.
upvoted 1 times
...
Dawn6699
1 year, 3 months ago
Selected Answer: A
Agree on A, because legal department normally does not proactively check every law relates to projects every day. PM should review it with legal department instead.
upvoted 1 times
...
noppy
1 year, 3 months ago
This question is highly flawed or missing something important. How can we determine what has happened based solely on the information provided in the question? Many participants are suggesting C as the answer, but how can we deduce from the given scenario that the "legal department has not disseminated" the information? It could be "legal department has disseminated". Then it was due to A, or D could also be a possibility. Additionally, B could be the answer as well. Ultimately, based on the sentences provided in this question, we cannot infer anything. Therefore, I consider it a highly flawed question, and any of the options could be the answer or none of them could be the answer.
upvoted 2 times
...
RevZig67
1 year, 5 months ago
Selected Answer: C
I'll go with C
upvoted 1 times
...
Hung3102
1 year, 5 months ago
C is ans
upvoted 1 times
...
sanjiiv
1 year, 6 months ago
Selected Answer: A
I will go with A, reviewing the contract is PM job and he should add the right stakeholder to review the contract including the Legal team which is always a part of contracting.
upvoted 2 times
...
PMPStudent
1 year, 9 months ago
Selected Answer: C
I will go with C. The team should not have any knowledge on the legality of the contracts
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...