The sponsor is supportive in leveraging agile approaches. The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders. What should the project manager do first?
A.
Determine which agile software tools will be required to support agile delivery within the organization
B.
Select a current predictive project, define the approach, and provide agile training to execute the remainder of the project
C.
Start with a pilot project of appropriate complexity, and provide agile training to those who are impacted
D.
Determine how to transform the organization using agile techniques, including organizational training and communications
The project manager should **C. Start with a pilot project of appropriate complexity, and provide agile training to those who are impacted**. Starting with a pilot project allows the team to gain practical experience with agile methodologies in a controlled environment. This can help to identify potential challenges and solutions before rolling out the agile approach on a larger scale. Providing training to those impacted ensures that everyone has the necessary knowledge and skills to work effectively in an agile environment. This approach can also help to build buy-in from team members and stakeholders as they see the benefits of agile firsthand.
Write answer is D. Determine how to transform the organization using agile techniques, including organizational training and communications. First you must train them before start a project to know what they have to handle.
Pilot project of appropriate complexity is a big cost/time activity, how u get cost for it, why stakeholder/project team will work on it.
Best option is D.
C. Start with a pilot project of appropriate complexity, and provide agile training to those who are impacted.
When transitioning to agile approaches and trying to gain buy-in from project team members and stakeholders, it's often advisable to start with a pilot project. This pilot project should be of an appropriate size and complexity to serve as a test case for the agile approach within your organization.
First step will not be A.
Provide Agile Training (Option C)
Start a Pilot Project (Option C)
Determine Agile Software Tools (Option A): As the team gains experience through the pilot project, the need for specific agile software tools may become evident. These tools can help streamline agile processes, enhance collaboration, and provide visibility into work. Determining the right tools to support agile practices is a natural progression after the team has received training and started working on a pilot project.
Option D: Transforming organizational training and communication to support agile methodologies is complex and also requires careful planning, stakeholder engagement, and a clear change management strategy. So not a good idea to start with a complex project.
Better to experiment the agile practices with a new less complex project and gain buy in from stakeholders with its results first.
While option D (Determine how to transform the organization using agile techniques, including organizational training and communications) is a valid consideration for introducing agile practices and approaches across the organization, it's usually a more comprehensive and longer-term effort. It involves transforming the entire organizational culture and processes to align with agile principles.
The answer is D. This refers to PMBOK 7th edition 3.4 the tailoring process. The steps are select initial development approach (Which in this case is Agile), Tailor for organization, then tailor for project, and then implement ongoing improvement. The question asks what you should do first.
This approach allows the project manager to demonstrate the benefits of the agile approach in acontrolled environment and provide hands-on training to the team members and stakeholders,which will help them to understand the approach and how to apply it effectively. This also allows totest the tools and processes that will be used in the agile approach, and to make adjustments asnecessary before implementing it on a larger scale.
C. Start with a pilot project of appropriate complexity, and provide agile training to those who are impacted
Starting with a pilot project of appropriate complexity and providing agile training to those who are impacted is the best way to roll out agile approaches and gain buy-in from both project team members and stakeholders. This approach allows for a controlled testing of the agile approach in a low-risk environment, and provides an opportunity to demonstrate the benefits of the approach to stakeholders. It also allows for the identification of any issues or challenges that may arise during the pilot project, which can be addressed before scaling up the approach to larger projects
For those who are saying "D", is there a word in the answer that I am missing? "Determine how to transform the organization using agile techniques, including organizational training and communications." Transforming the organization using Agile techniques and educating the organization on Agile techniques are two different animals.
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
tonybuivannghia
9 months, 1 week agojosephsafiran
1 year, 2 months agoodylec
1 year, 4 months agocertificate988
1 year, 4 months agocb4a6c4
1 year, 5 months agoOnly12go
1 year, 6 months agoAish_
1 year, 8 months agoAish_
1 year, 8 months agoAish_
1 year, 8 months agomythicalfiber
1 year, 8 months agoAish_
1 year, 8 months agokevindebruyne
1 year, 8 months agoSteAle
1 year, 9 months agoSteAle
1 year, 9 months agokevzzz
1 year, 9 months agoThirukj
1 year, 10 months agoadingmaki
1 year, 6 months agoJYKL88
2 years agoHung3102
2 years agoMaccaoidh
2 years agoPaulPMP
2 years, 1 month ago