After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration. At this point, the project manager learns about a possible change in regulations that would prevent the product launch.
What should the project manager do to realize benefits?
guyver0523
Highly Voted 2 years agorajeshtk
2 years ago[Removed]
1 year, 11 months agoPaulPMP
1 year, 6 months agoKim222
Most Recent 3 weeks, 2 days agohoomz
7 months, 1 week agojosephsafiran
7 months, 3 weeks agoOnly12go
11 months, 1 week agoDavid983
11 months, 1 week agoAish_
1 year, 1 month agoThirukj
1 year, 3 months agorajeshtk
1 year, 5 months agoAlphasham
1 year, 11 months agovictory108
1 year, 11 months agoAdala
2 years ago