Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 490 discussion

Actual exam question from PMI's PMP
Question #: 490
Topic #: 1
[All PMP Questions]

At the end of a project with multiple suppliers, the project manager is reviewing the closing process and finds that an unexpected financial balance is remaining.
What will help the project manager understand why this has occurred?

  • A. Project audit
  • B. Lessons learned
  • C. Organizational process assets
  • D. Procurement audit
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Seyi22
Highly Voted 1 year, 5 months ago
A is correct. A project audit is the most appropriate choice to help the project manager understand why an unexpected financial balance is remaining at the end of a project with multiple suppliers. A project audit is a comprehensive review of the project's performance, processes, and outcomes. It aims to identify any discrepancies, variances, or issues that occurred during the project execution. By conducting a project audit, the project manager can examine the financial records, procurement processes, contracts, and interactions with suppliers to identify the reasons behind the unexpected financial balance. The audit will provide insights into any financial discrepancies, such as payments made to suppliers, invoicing errors, cost overruns, or other financial issues that might have contributed to the remaining balance. From ChatGPT
upvoted 9 times
...
Amirov
Most Recent 2 weeks, 6 days ago
Selected Answer: D
While a project audit examines the overall performance and management of the project, it may not focus specifically on procurement activities or financial discrepancies related to suppliers.
upvoted 1 times
...
Kim222
2 months, 3 weeks ago
I Think this is A
upvoted 1 times
...
Kim222
3 months, 2 weeks ago
Selected Answer: D
A is to audit the overall process of the project, not the budget.
upvoted 1 times
...
tonybuivannghia
4 months ago
Selected Answer: D
D. Procurement audit A procurement audit is conducted to review the procurement process and contracts to ensure that all aspects of the procurement process have been properly administered and closed out. It helps in verifying that all payments have been made, all deliverables have been received, and any remaining financial balances are properly accounted for. Therefore, if a project manager finds an unexpected financial balance remaining at the end of a project involving multiple suppliers, conducting a procurement audit would be the most appropriate action to understand why this has occurred.
upvoted 2 times
...
c8ee0e6
4 months, 1 week ago
Selected Answer: D
A procurement audit dives deep into the procurement activities related to the suppliers involved in the project. This includes reviewing: Contracts and purchase orders Invoices and payments made Supplier performance Any changes or amendments made to contracts By examining these aspects, the procurement audit can help identify potential causes for the unexpected balance, such as: Overpayment to a supplier Missed discounts or rebates Unrecorded credits Unclear contract terms leading to misinterpretations on scope or deliverables Once the reason for the discrepancy is identified, corrective actions can be taken, and the financial closure process can be finalized accurately.
upvoted 1 times
...
Bruce_Liu
8 months, 4 weeks ago
Selected Answer: A
A cover D already, A is the most comprehensive one. D only cover procurement itself but never consider cost consumed from project team.
upvoted 1 times
...
rshankhwa
9 months ago
Selected Answer: A
A is correct.
upvoted 1 times
...
Only12go
1 year, 1 month ago
Selected Answer: D
D. Procurement audit A procurement audit is a process used to review and assess the procurement processes, contracts, and financial aspects of a project involving multiple suppliers. It helps the project manager understand the financial transactions, payments, and any unexpected financial balances that may have occurred during the project. The procurement audit provides insights into the performance of suppliers, contract compliance, and any discrepancies in payments or invoices. It can help identify the reasons behind unexpected financial balances and ensure that all procurement-related matters are properly closed out.
upvoted 2 times
...
victory108
1 year, 2 months ago
Selected Answer: D
D. Procurement audit
upvoted 1 times
...
Aish_
1 year, 3 months ago
Selected Answer: A
unexpected financial balance may not be specifically because of multiple suppliers. So its better to do an overall audit.
upvoted 3 times
...
kevzzz
1 year, 3 months ago
Selected Answer: A
A project audit is a structured review process of a project's performance, progress, and outcome against pre-defined objectives, goals, and criteria. For a project manager, a project audit is really crucial as labor, time, and money are all at stake.
upvoted 1 times
...
Dawn6699
1 year, 5 months ago
Selected Answer: D
D. Procurement audit would be the best option for understanding why an unexpected financial balance is remaining at the end of a project with multiple suppliers. Procurement audits review procurement-related activities such as the acquisition of goods or services, and the processes used throughout the procurement to identify any discrepancies in costing, cost estimating, contract terms, quality-based selection, supplier’s performance over the contract period, etc. Thus, a procurement audit can help the project manager identify the root cause of the unexpected financial balance remaining and whether it has resulted from procurement-related activities. From chartGPT
upvoted 1 times
...
Thirukj
1 year, 5 months ago
Selected Answer: A
A is correct
upvoted 1 times
Thirukj
1 year, 5 months ago
I go back and now say it is D
upvoted 1 times
...
...
JYKL88
1 year, 7 months ago
Selected Answer: D
D, procurement audit
upvoted 3 times
...
Davonos
2 years, 1 month ago
I agree D is correct
upvoted 1 times
...
GDT001
2 years, 1 month ago
Selected Answer: A
I think A is correct as it will covers all project activities that could contributed to the budget balance..
upvoted 2 times
rajeshtk
2 years, 1 month ago
Invoice approvals and disputes is one of the steps in procurement audit.
upvoted 2 times
...
[Removed]
2 years, 1 month ago
I think its D. The PMBOK and related writing will tell you that there are plenty of processes that influence project budget. However, budget isn't always financial, schedules and time also have a budget. While the budget can be influenced in other knowledge groups, the financial portion is exclusively in procurement.
upvoted 6 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...