Important projects in the portfolio backlog need to be delivered. Budget estimates are needed to prioritize the projects. How should the project budgets be estimated?
A.
The project is decomposed into features and based on the feature value and the velocity of the team, the team provides the estimate
B.
Budget estimates are provided based on the experience of the sponsor, product owner and team facilitator
C.
The team facilitator uses historical data and arrives at an estimate based on the nature of the project.
D.
The product owner obtains all project details and based on the team's experience and velocity provides a budget estimate
But the team only provides the effort and time. The question is asking about estimating the budget. It should be B - Project Manager, PO & Team, I believed. Any thoughts?
Rem, this is a portfolio backlog and prioritization is done at the portfolio level, so most likely the projects have not started. so there is no team, no product owner.
All the team of the project with the sponsor, PM and PO make the estimation of the budget. Each member make the estimation about his part collects the data and completes the estimation of the budget.
1. The question doesn´t talk abuot Prject Team decide about the product backlog, it just ask about how the Project budget must be estimated ""How should the project budgets be estimated?"".
2. Budget is performed by accumulating all the Project Costs and Project Cost is performed by estimating each story user by the Project Team.
Based on Andrew Ramadyal, best approach the team for schedule, cost, and work estimates.
B is wrong.
Budget estimates are provided based on the experience of the sponsor, product owner and team facilitator
1.) Seriously? Ask the sponsor for budget estimate of YOUR project?
2.) Product Owner doesn't need to worry himself of cost. This is from PMI studyhall.
IT'S THE TEAM WHO BEST KNOWS THE ESTIMATE. NOT THE SPONSOR, PRODUCT OWNER, OR THE FACILITATE. THEY ARE CONSIDERED THE SME!!!! NOT THE PROJECT LEADS!!!!
The Portfolio Backlog is a Kanban system that is used to capture and manage the business and enabler epics intended to create and evolve the portfolio's products, services, and solutions.
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
emelba
Highly Voted 2 years agoaqz_111
1 year, 9 months agoYSO34
Highly Voted 2 years, 7 months agorajeshtk
2 years, 7 months agokevindebruyne
1 year, 8 months agobe_zzo
Most Recent 4 days, 10 hours agod370e49
7 months, 1 week agoKim222
7 months, 2 weeks agoKim222
7 months, 2 weeks agotonybuivannghia
8 months, 4 weeks agoGetange
10 months, 3 weeks agosegatarasov
1 year, 1 month agoBruce_Liu
1 year, 1 month agoodylec
1 year, 4 months ago[Removed]
1 year, 5 months agoDavid983
1 year, 5 months agoOnly12go
1 year, 6 months agoadingmaki
1 year, 6 months agoadingmaki
1 year, 6 months agonilopo
1 year, 1 month agovictory108
1 year, 7 months agoAish_
1 year, 8 months agokevzzz
1 year, 8 months ago