Exam PMP topic 1 question 489 discussion

Actual exam question from PMI's PMP
Question #: 489
Topic #: 1
[All PMP Questions]

Important projects in the portfolio backlog need to be delivered. Budget estimates are needed to prioritize the projects.
How should the project budgets be estimated?

  • A. The project is decomposed into features and based on the feature value and the velocity of the team, the team provides the estimate
  • B. Budget estimates are provided based on the experience of the sponsor, product owner and team facilitator
  • C. The team facilitator uses historical data and arrives at an estimate based on the nature of the project.
  • D. The product owner obtains all project details and based on the team's experience and velocity provides a budget estimate
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
emelba
Highly Voted 1 year, 5 months ago
agree with B, only bosses decide about portfolio, not teams
upvoted 7 times
aqz_111
1 year, 2 months ago
agree B, because A is the process for story point estimation which is not budget estimation
upvoted 2 times
...
...
YSO34
Highly Voted 2 years ago
Selected Answer: A
A is right answer
upvoted 5 times
rajeshtk
1 year, 12 months ago
Agree. A is the correct answer. For any engagement, team provides the estimate.
upvoted 3 times
kevindebruyne
1 year, 1 month ago
But the team only provides the effort and time. The question is asking about estimating the budget. It should be B - Project Manager, PO & Team, I believed. Any thoughts?
upvoted 1 times
...
...
...
tonybuivannghia
Most Recent 1 month, 2 weeks ago
Selected Answer: A
A is correct
upvoted 2 times
...
Getange
3 months, 1 week ago
Rem, this is a portfolio backlog and prioritization is done at the portfolio level, so most likely the projects have not started. so there is no team, no product owner.
upvoted 1 times
...
segatarasov
6 months ago
in my opinion, A is correct here
upvoted 1 times
...
Bruce_Liu
6 months, 1 week ago
Selected Answer: A
This questions is highlighting its criticality, then we should use the more accurate approach instead of just base on experience.
upvoted 2 times
...
odylec
8 months, 3 weeks ago
Selected Answer: B
All the team of the project with the sponsor, PM and PO make the estimation of the budget. Each member make the estimation about his part collects the data and completes the estimation of the budget.
upvoted 1 times
...
[Removed]
9 months, 3 weeks ago
Selected Answer: A
estimate from the team usually more accurate than the sponsor and team facilitator.
upvoted 1 times
...
David983
10 months ago
Selected Answer: A
1. The question doesn´t talk abuot Prject Team decide about the product backlog, it just ask about how the Project budget must be estimated ""How should the project budgets be estimated?"". 2. Budget is performed by accumulating all the Project Costs and Project Cost is performed by estimating each story user by the Project Team.
upvoted 1 times
...
Only12go
10 months, 3 weeks ago
Selected Answer: A
B doesnt make sense to me why are we budgeting for the staff to get projects done, priority would be on the deliverables.
upvoted 1 times
...
adingmaki
11 months ago
Selected Answer: B
Based on Andrew Ramadyal, best approach the team for schedule, cost, and work estimates. B is wrong. Budget estimates are provided based on the experience of the sponsor, product owner and team facilitator 1.) Seriously? Ask the sponsor for budget estimate of YOUR project? 2.) Product Owner doesn't need to worry himself of cost. This is from PMI studyhall. IT'S THE TEAM WHO BEST KNOWS THE ESTIMATE. NOT THE SPONSOR, PRODUCT OWNER, OR THE FACILITATE. THEY ARE CONSIDERED THE SME!!!! NOT THE PROJECT LEADS!!!!
upvoted 1 times
adingmaki
11 months ago
THE TEAM ARE CONSIDERED THE SME***
upvoted 1 times
nilopo
6 months ago
Why on earth you selected the answer as B and supporting option A?
upvoted 1 times
...
...
...
victory108
1 year ago
Selected Answer: A
A. The project is decomposed into features and based on the feature value and the velocity of the team, the team provides the estimate
upvoted 1 times
...
Aish_
1 year ago
Selected Answer: B
Start with Experience-Based Estimation (Option B) at a high level to quickly assess the overall budget requirements.
upvoted 2 times
...
kevzzz
1 year, 1 month ago
Selected Answer: B
The Portfolio Backlog is a Kanban system that is used to capture and manage the business and enabler epics intended to create and evolve the portfolio's products, services, and solutions.
upvoted 2 times
...
GinniSingh
1 year, 1 month ago
Selected Answer: B
It is about Portfolio Backlog.. which is dealt by leads
upvoted 2 times
...
Hung3102
1 year, 5 months ago
A is ans
upvoted 2 times
...
alltaken
1 year, 9 months ago
Selected Answer: B
B make sense. Because Budget estimate and Cost estimate are 2 different things.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...