During a documentation audit of an international company, it was identified that the last version of the project schedule was from one month ago even though the project manager knew it was recently updated.
How should the project manager have handled documentation for the project?
KennyMuffins
Highly Voted 1 year, 2 months agoKim222
Most Recent 7 months, 4 weeks agoPiz7
10 months, 1 week agod482858
1 year agoBruce_Liu
1 year, 3 months agojosephsafiran
1 year, 3 months agoUncle_Lucifer
1 year, 6 months agoOnly12go
1 year, 6 months agoadingmaki
1 year, 6 months agoDavid983
1 year, 6 months agoDavid983
1 year, 6 months ago1234abcdefgh
1 year, 7 months agovictory108
1 year, 8 months agoAish_
1 year, 8 months agoJamrock
1 year, 8 months agoSteAle
1 year, 9 months agoNeil20
1 year, 10 months agorknowles
1 year, 10 months ago