Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 467 discussion

Actual exam question from PMI's PMP
Question #: 467
Topic #: 1
[All PMP Questions]

During a documentation audit of an international company, it was identified that the last version of the project schedule was from one month ago even though the project manager knew it was recently updated.
How should the project manager have handled documentation for the project?

  • A. Updated the project management plan regularly and had it securely shared with all stakeholders
  • B. Assigned a project team member to ensure all project documentation was updated
  • C. Reviewed the risk register to identify a response plan for the audit
  • D. Kept documentation in the project management information system (PMIS), and shared it with appropriate stakeholders
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
2 months ago
Selected Answer: D
This is D. Updating your project management information system is important to maintain consistency.
upvoted 1 times
...
Piz7
4 months, 1 week ago
Selected Answer: A
This is A
upvoted 1 times
...
d482858
6 months, 2 weeks ago
The problem the PM had was the documentation wasn't updated regularly . You can still store the documents in the PMIS and not update them frequently. I chose A:
upvoted 1 times
...
KennyMuffins
8 months, 2 weeks ago
Selected Answer: D
Correct me if i am mistaken of the english in the question. "latest version was one month ago", but "project manager knew it was recently updated" Doesnt this imply that the project schedule was recently updated but PM is referencing the wrong version? Wouldnt this then mean that proper version control is needed to ensure artifacts are updated and latest version is acquired.
upvoted 4 times
...
Bruce_Liu
9 months, 1 week ago
Selected Answer: A
Question is asking for regular update to keep doc up to date but not have to use document system.
upvoted 1 times
...
josephsafiran
9 months, 3 weeks ago
Selected Answer: A
Keeping documentation in the project management information system (PMIS) and sharing it with appropriate stakeholders (Option D) is a good practice, but it should be coupled with regular updates to ensure that the information remains current.
upvoted 1 times
...
Uncle_Lucifer
1 year ago
Project management plan is for planning. updating management plan has nothing to do with updating the actual project document. --->D
upvoted 3 times
...
Only12go
1 year ago
Selected Answer: D
Option D, on the other hand, specifically recommends keeping documentation in the project management information system (PMIS). A PMIS is designed to centrally store, update, and distribute project information, including the project schedule. By keeping documentation in the PMIS and sharing it with the appropriate stakeholders, the project manager would ensure that stakeholders have access to the most recent version of the project schedule, directly addressing the issue identified in the audit.
upvoted 2 times
...
adingmaki
1 year ago
Selected Answer: D
be careful with the word all. I work with google and we don't share some documents with project coordinators. These stakeholders could change the documents, delete it, alter, tamper, and etc. D is correct.
upvoted 2 times
...
David983
1 year ago
Selected Answer: A
Agree with A more suitable than D, option D doesn´t mention "updated documentation" and just said "Kept Documnt",
upvoted 1 times
David983
1 year ago
Switch to D, adingmaki is right, the words "all stakeholders" do the option A a wrong option
upvoted 1 times
...
...
1234abcdefgh
1 year, 1 month ago
Selected Answer: D
D. Kept documentation in the project management information system (PMIS), and shared it with appropriate stakeholders
upvoted 1 times
...
victory108
1 year, 2 months ago
Selected Answer: D
D. Kept documentation in the project management information system (PMIS), and shared it with appropriate stakeholders
upvoted 1 times
...
Aish_
1 year, 2 months ago
Selected Answer: D
Project Management Information Systems (PMIS) often include version control features to track changes and revisions made to project documents and artifacts. This helps in maintaining a history of updates and ensuring that the most recent and accurate information is available to the project team.
upvoted 2 times
...
Jamrock
1 year, 2 months ago
Selected Answer: A
the reasons others give for picking D. are just odd, to put it mildly. Answer to A may be misleading BUT not seeing that D. does not address the question is bad reading comprehension. PMIS approach does not guarantee having the PIMS version updated regularly.
upvoted 1 times
...
SteAle
1 year, 3 months ago
Selected Answer: D
The project management plan doesn't include a project schedule. It includes the schedule baseline. So, the best option is D
upvoted 2 times
...
Neil20
1 year, 4 months ago
Selected Answer: A
A is correct!
upvoted 2 times
...
rknowles
1 year, 4 months ago
Selected Answer: A
The PMBOK states that when a project schedule is updated, the corresponding changes should be applied to the project management plan.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...