During a documentation audit of an international company, it was identified that the last version of the project schedule was from one month ago even though the project manager knew it was recently updated.
How should the project manager have handled documentation for the project?
Kim222
2 months agoPiz7
4 months, 1 week agod482858
6 months, 2 weeks agoKennyMuffins
8 months, 2 weeks agoBruce_Liu
9 months, 1 week agojosephsafiran
9 months, 3 weeks agoUncle_Lucifer
1 year agoOnly12go
1 year agoadingmaki
1 year agoDavid983
1 year agoDavid983
1 year ago1234abcdefgh
1 year, 1 month agovictory108
1 year, 2 months agoAish_
1 year, 2 months agoJamrock
1 year, 2 months agoSteAle
1 year, 3 months agoNeil20
1 year, 4 months agorknowles
1 year, 4 months ago