Question #: 596
Topic #: 1
[All PMP Questions]

During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible.
What approach should be used in this situation?

  • A. The team facilitator gets support from external team members.
  • B. The team members bring in a specialist to help them
  • C. The product owner moves it to the product backlog.
  • D. The cross-functional team member work together to complete the activity
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Mgaidiwahid
1 month, 1 week ago
Answer D
upvoted 1 times
...
DavidTri
4 months, 2 weeks ago
Selected Answer: B
Project team know exactly what is problem and who helpful to help them
upvoted 1 times
...
Delab202
9 months, 3 weeks ago
Selected Answer: D
D. The cross-functional team members work together to complete the activity. This approach leverages the diverse skills and expertise within a cross-functional team to tackle the complexity of the task. By collaborating closely, team members can identify and implement solutions more efficiently than working in isolation or waiting for external help. This method fosters innovation, accelerates problem-solving, and ensures that different perspectives are considered in addressing the complexity of the activity. It also aligns with agile principles, emphasizing teamwork, collaboration, and the ability to adapt to changing circumstances.
upvoted 3 times
...
KennyMuffins
9 months, 4 weeks ago
Selected Answer: D
Bringing in external support or specialists (options A and B) may introduce delays and go against the principles of a self-organizing team.
upvoted 1 times
...
certificate988
11 months, 3 weeks ago
Selected Answer: D
Option B is better but can team members decide to bring in specialist. I think it needs to be decided by PM. That is why D is next better choice as cross-functional team member is expected to have more skill to solve the problem. If B is the answer then it should say PM instead of team members.
upvoted 1 times
...
xcjxcj
11 months, 4 weeks ago
Selected Answer: D
https://www.examtopics.com/discussions/pmi/view/56747-exam-pmp-topic-1-question-1848-discussion/
upvoted 1 times
...
Perezi
1 year ago
Selected Answer: D
Is it the teams responsibility to hire a specialist?
upvoted 1 times
...
nemm235
1 year, 1 month ago
Every one selected D but apparently B look more suitable in this scenario. because If we have already cross-functional team working together and an activity become more complex need to complete quickly. in this case need specialist(subject meter expert). please correct me if I am wrong....
upvoted 3 times
...
victory108
1 year, 2 months ago
Selected Answer: D
D. The cross-functional team member work together to complete the activity
upvoted 1 times
...
AmitBI
1 year, 2 months ago
Selected Answer: D
First try to involve cross functional team members to take their views and if not solved then take help from specialist.
upvoted 1 times
...
Aish_
1 year, 3 months ago
Selected Answer: D
O Option D - having the cross-functional team members work together to complete the activity. This approach encourages collaboration, knowledge sharing, and leveraging the diverse skills and expertise of the team to tackle the complex activity effectively. By working together, the team members can brainstorm solutions, support each other, and collectively find the most efficient way to deliver the work in the shortest time possible.
upvoted 2 times
...
TONYJAVI
1 year, 4 months ago
Selected Answer: D
Should be D. It's an Agile common. "Swarming. A technique in which multiple team members focus collectively on resolving a specific impediment."
upvoted 2 times
...
SynikalDemon
1 year, 4 months ago
We can go with D, but the real world answer is B.
upvoted 1 times
...
Thirukj
1 year, 5 months ago
Answer is D
upvoted 2 times
...
Faozi
1 year, 5 months ago
Selected Answer: D
What's happening to exam topics.
upvoted 3 times
...
RevZig67
1 year, 7 months ago
Selected Answer: D
The cross-functional team members should work together to complete the activity. This approach promotes collaboration and cross-functional teamwork, which can help identify and address any complexities that arise during the iteration. The team can leverage each other's strengths and knowledge to solve the problem and complete the activity in the shortest time possible. Bringing in an external specialist or moving the work to the backlog may cause delays and disrupt the team's momentum.
upvoted 3 times
...
Hung3102
1 year, 7 months ago
I will go with B
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...