A project manager led the implementation of an electronic invoicing project that has just been completed. The financial manager communicated that the team discovered three invoices with errors.
Which two documents should the project manager update as soon as possible? (Choose two.)
[Removed]
Highly Voted 1 year, 11 months agoJYKL88
Highly Voted 1 year, 4 months agoParamak
Most Recent 4 weeks, 1 day agoKim222
1 month, 2 weeks agourso2703
5 months, 3 weeks agoDelab202
7 months, 3 weeks agolezgino
9 months, 1 week agodinodragon
3 months, 2 weeks agomesacgon
9 months, 3 weeks agocertificate988
9 months, 3 weeks agoDavid983
10 months, 2 weeks agoAymen1989
10 months, 3 weeks agoSumbo
11 months, 2 weeks agovictory108
1 year agoAYZ
1 year, 1 month agoAish_
1 year, 1 month agoAish_
1 year, 1 month agoTONYJAVI
1 year, 1 month ago