Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 616 discussion

Actual exam question from PMI's PMP
Question #: 616
Topic #: 1
[All PMP Questions]

A client mentioned that in the past 2 months, they have not been invoiced for completed work. The client has communicated that they will release the funds for other activities it the invoices are not sent.
What should the project manager do next?

  • A. Work with the client and agree on a schedule to provide them with the invoices
  • B. Reach out to the billing team and instruct them to issue the invoices immediately
  • C. Review the previous billing information and prepare a corrective action plan
  • D. Communicate and inform the client to go ahead and release the funds
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
RevZig67
Highly Voted 1 year, 5 months ago
Selected Answer: A
The project manager should work with the client to understand the reason behind the delay in invoicing and agree on a schedule to provide the invoices. This will help to build trust and ensure that the funds are released. Simply instructing the billing team to issue the invoices immediately without understanding the reason for the delay may not solve the underlying issue and may lead to further problems. Reviewing previous billing information and preparing a corrective action plan may be necessary, but it should not be the first step taken in this situation. Communicating and informing the client to go ahead and release the funds without providing the invoices may not be a good approach as it may create doubts in the client's mind about the project's financial management.
upvoted 6 times
...
sweety433
Most Recent 2 weeks, 5 days ago
Can Option B the answer ? As it ties on the urgency. Delayed invoicing could pose a risk to project cash flow. The PMBOK advocates for taking immediate action to mitigate risks ?
upvoted 1 times
...
Kim222
2 weeks, 6 days ago
Selected Answer: C
According to PMI, everything needs to be examined for its root cause. You need to check if what the customer said is true and figure out what it is before you can proceed to the next step. Setting a schedule first is like proceeding without even knowing what it is. Root cause!!! Don't forget.
upvoted 1 times
...
Abdelmonm
7 months, 3 weeks ago
Selected Answer: A
It's crucial for the project manager to address the client's concerns regarding the delayed invoices promptly. Working collaboratively with the client to understand their expectations and agreeing on a schedule for invoicing demonstrates proactive communication and a commitment to resolving the issue. This approach helps maintain a positive client relationship and ensures that financial matters are handled effectively.
upvoted 1 times
...
UppersquareCapital
8 months, 3 weeks ago
Selected Answer: A
A. Work with the client and agree on a schedule to provide them with the invoices. The project manager should collaborate with the client to address the invoicing issue, understand their expectations, and agree on a schedule for providing the invoices. This approach ensures effective communication and helps in preventing any potential disruptions to the project due to delayed invoicing.
upvoted 1 times
...
odylec
9 months ago
Selected Answer: C
C is the answer. You must first now the billing history and after that speak with the client
upvoted 2 times
...
Only12go
11 months ago
Selected Answer: C
In this situation, the immediate priority is to ensure accurate billing and rectify the oversight while maintaining trust and transparency with the client. Given the choices: C. Review the previous billing information and prepare a corrective action plan. This is the best approach. Before any action is taken, it's essential to understand the root cause of the oversight. By reviewing previous billing information, the project manager can verify whether the work was indeed completed and ensure the accuracy of the upcoming invoices. Preparing a corrective action plan will also demonstrate to the client that steps are being taken to rectify the mistake and prevent similar occurrences in the future.
upvoted 2 times
...
adingmaki
11 months, 1 week ago
REVIEW FIRST SO YOU CAN PREPARE AND SAY SOMETHING IN THE MEETING WITH THE CLIENT. OMG. PUT YOURSELF IN THE SITUATION. THE CLIENT PRESSURED YOU AND YOU CALL IMMEDIATELY? IS THAT SOME HOW OF YOU PM's WORK IN REAL LIFE?
upvoted 3 times
nilopo
6 months, 1 week ago
Why on earth you are so furious with your answers. Try to understand the situation "The client has communicated that they will release the funds for other activities it the invoices are not sent". There is an urgency and the next thing you do is to work out a solution by negotiating with the client before he releases the funds for other activities. who knows how long you would keep reviewing the previous billing and keep working on corrective action plan. As a PM you have other things to do as well, so concentrate on the what the situation and take expert judgement call!!
upvoted 1 times
...
xcjxcj
8 months, 2 weeks ago
Tell client asap and ask internally. In this case client will give a deadline, 1day or 3 days, then you work internally with billing team.
upvoted 1 times
...
...
victory108
12 months ago
Selected Answer: A
A. Work with the client and agree on a schedule to provide them with the invoices
upvoted 1 times
...
AstridN
1 year, 2 months ago
Selected Answer: C
Check the history and try to figure smth out
upvoted 2 times
...
kevzzz
1 year, 3 months ago
Selected Answer: C
What should the PM do NEXT? Review the previous billing... You don't just jump in there and correct something blindly.
upvoted 2 times
...
JYKL88
1 year, 4 months ago
answer should be C The project manager should review the previous billing information to identify any issues or gaps in the invoicing process. Once they have identified the cause of the problem, they can then develop a corrective action plan to address it. This approach will help to ensure that the client's concerns are addressed and that the project can continue without any further delays.
upvoted 1 times
...
poohwinniewong
1 year, 10 months ago
Why the ans is not A to mutually agree on a schedule?
upvoted 1 times
...
rajeshtk
2 years ago
why can't the answer be A?
upvoted 1 times
leo_gold
1 year, 9 months ago
You cant just go ahead and believe what is the client saying - you will need to review billing to confirm there is an issue on your end before anything else.
upvoted 4 times
...
YSO34
2 years ago
this is not a forgetfulness but something else, the PM has to follow the process and so the last invoice information
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...