exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 611 discussion

Actual exam question from PMI's PMP
Question #: 611
Topic #: 1
[All PMP Questions]

DRAG DROP -
An experienced project manager is overseeing a merger and acquisition project. The project manager reacted differently to different threats identified on the project.
Drag the mitigation strategy on the left to the project manager's actions on the night.
Select and Place:

Show Suggested Answer Hide Answer
Suggested Answer:

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
EfaChux
7 months, 3 weeks ago
Answers are correct
upvoted 1 times
...
chlaithem
9 months, 2 weeks ago
Mitigate: The project manager took proactive actions (conducting tests) to reduce the probability of the threat occurring, demonstrating a mitigation strategy. Avoid: The project manager deemed the threat severe and altered project strategies (reducing scope) to eliminate the risk entirely, indicating an avoidance strategy. Transfer: The project manager identified the threat and shared responsibility with a third party (insurance) to lessen its impact, exemplifying a transfer strategy. Accept: The project manager acknowledged the threat but decided to monitor it rather than take immediate action, accepting the risk with awareness. Escalate: The project manager recognized the threat as beyond their control and escalated it to a higher authority for appropriate handling.
upvoted 1 times
...
sheisblessed2022
10 months, 2 weeks ago
Mitigate --> The project manager analyzed the threat, took action to reduce the probability of occurrence, and conducted some additional tests Accept --> The project manager determined the threat was severe and acted promptly to handle this risk by changing project strategies and reducing project scope Transfer --> The project manager identified the threat, discussed it with the sponsor, and bought an insurance plan to handle it Avoid --> The project manager identified the threat and decided to review it periodically rather than take action Escalate --> The project manager studied the threat and found it is out of their authority and scope
upvoted 2 times
...
Aymen1989
11 months, 3 weeks ago
Correct answers
upvoted 2 times
...
victory108
1 year, 1 month ago
Mitigate --> The project manager analyzed the threat, took action to reduce the probability of occurrence, and conducted some additional tests Avoid --> The project manager determined the threat was severe and acted promptly to handle this risk by changing project strategies and reducing project scope Transfer --> The project manager identified the threat, discussed it with the sponsor, and bought an insurance plan to handle it Accept --> The project manager identified the threat and decided to review it periodically rather than take action Escalate --> The project manager studied the threat and found it is out of their authority and scope
upvoted 3 times
UppersquareCapital
9 months, 3 weeks ago
You are absolutely correct.
upvoted 1 times
...
...
kayyaly
1 year, 1 month ago
the provided answer is correct
upvoted 3 times
...
RISHAB1234
1 year, 1 month ago
Mitigation Strategy: Mitigate Project Manager's Actions: The project manager determined the threat was severe and acted promptly to handle this risk by changing project strategies and reducing project scope. Mitigation Strategy: Avoid Project Manager's Actions: The project manager identified the threat and decided to review it periodically rather than take action. Mitigation Strategy: Transfer Project Manager's Actions: The project manager identified the threat, discussed it with the sponsor, and bought an insurance plan to handle it. Mitigation Strategy: Accept Project Manager's Actions: The project manager studied the threat and found it is out of their authority and scope. Mitigation Strategy: Escalate Project Manager's Actions: The project manager analyzed the threat, took action to reduce the probability of occurrence, and conducted some additional tests.
upvoted 1 times
...
rajeshtk
2 years, 1 month ago
Why the 4th one is transfer? Is it due to the risk is owned by the stakeholder?
upvoted 1 times
Jeancarlos1
2 years ago
using insurance is transferring risk making the insurance agency responsible for the risk.
upvoted 4 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago