Exam PMP topic 1 question 4 discussion

Actual exam question from PMI's PMP
Question #: 4
Topic #: 1
[All PMP Questions]

A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.
What should the project manager do?

  • A. Meet with the design team manager to inform them of the current status and request an additional designer
  • B. Ask the software engineer to move forward without completing the important feature
  • C. Contact the design team manager and ask to reconsider the priority list based on the latest situation
  • D. Meet with the designer to share the current status and develop a solution to complete the task
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
NA1234567
Highly Voted 8 months, 1 week ago
Selected Answer: D
collaboration before escalation
upvoted 10 times
...
Princessviv96
Most Recent 3 days, 8 hours ago
Selected Answer: D
In my opinion D is the correct answer.it is important manager to reach out to the designer to come up with a solution for on how to complete the additional feature, this way they are able to complete both features in time for implementation as opposed to giving up one for the other as both are equally vital. hence, collaboration before escalation
upvoted 1 times
...
Firebonobono
1 month ago
Selected Answer: C
Collaborate Before Escalation This principle applies first when it can be resolved within the team! Since the issue is from another department, bypassing the design team manager and talking directly to the designer is an informal approach. Because in PMP, collaboration between stakeholders and following formal channels is important.
upvoted 1 times
...
Active_Learner420
2 months, 2 weeks ago
Selected Answer: C
As Designer is managed by FM, maybe he is working on priority list set by FM. Sequence of solving this problem: C-->D or C-->A--D B is wrong option
upvoted 1 times
...
FauziYusmin
2 months, 4 weeks ago
Selected Answer: D
By addressing the blocker swiftly and proactively managing the timeline, the project manager can help the team recover from the delay and stay on track to meet the critical release deadline.
upvoted 1 times
...
MSM
3 months, 1 week ago
Selected Answer: D
Meeting and discussing face to face is always a good option to resolve most of the issues.
upvoted 1 times
...
miffy_w
3 months, 2 weeks ago
Selected Answer: C
It is obviously a functional organizational structure, so PM has less or not much control over the team member. Talk to the designer team manager is the way to resolve the resources issue.
upvoted 2 times
...
MalikSaab
3 months, 4 weeks ago
Selected Answer: D
PM needs to have the direct communication with the team to ensure timely delivery
upvoted 1 times
...
crypto_dreams_medellin
4 months, 4 weeks ago
you need solutions and to better understand how to move forward before taking action
upvoted 1 times
...
fragar65
5 months, 4 weeks ago
D. communication is key. direct communication with the person responsible for the delay. assess the situation and move forward. C is also a good choice but you are avoiding handling the issue directly. This can also cause a delay in communication. communication is key.
upvoted 1 times
...
pop71
6 months, 1 week ago
In this scenario, the project manager should choose: C. Contact the design team manager and ask to reconsider the priority list based on the latest situation. Reasoning: Collaboration: Engaging with the design team manager fosters collaboration and ensures that both teams are aligned on priorities. Resource Allocation: By asking to reconsider the priority list, the project manager can identify critical tasks that need immediate attention, allowing the team to adapt quickly to the new urgency. Addressing Roadblocks: This approach directly addresses the roadblock affecting the project timeline and seeks to find a solution that can keep the project on track. While meeting with the designer (option D) is also a viable approach, it may not effectively resolve the larger issue of prioritization and resource allocation at the team level.
upvoted 1 times
...
LotToLearn
6 months, 1 week ago
correct is D as is directly talking about action and solution c is kind of PM shying away from responsibility and also the process will cause more delay
upvoted 2 times
...
Aditech
6 months, 1 week ago
D The project manager should immediately address the dependency issue by discussing it with the designer to understand the delay and explore potential solutions, such as reallocating resources or adjusting priorities. They should also communicate the urgency of the situation to relevant stakeholders and consider alternative approaches to ensure the timely completion of the feature and meet the release date. Adigun.
upvoted 2 times
...
Pragati06
6 months, 2 weeks ago
Correct answer is D.To collaborate with assigned designer and to work on solution
upvoted 1 times
...
AfricanTea
8 months, 2 weeks ago
Standup meetings is a feature for agile projects which we know as flexible. I will go with D because there is possibility that the designer has solutions to most of the challenges...
upvoted 1 times
...
Bry29
9 months, 3 weeks ago
Selected Answer: C
definitely C
upvoted 1 times
...
Jiyoung0301
10 months, 3 weeks ago
Selected Answer: C
C. I don't think it's pm's job to develop a solution.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago