Actual exam question from PMI's CAPM
Question #: 244
Topic #: 1
[All CAPM Questions]

A project manager is performing the procurement management process with three vendors. The project team is reviewing the requests for proposal (RFPs).
What type of procurement document is the RFP?

  • A. Bid document
  • B. Statement of work (SOW)
  • C. Source selection criteria
  • D. Independent cost estimate
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Vangelis_1980
1 month, 3 weeks ago
Selected Answer: A
A. Bid document An RFP (Request for Proposal) is essentially a bid document. It's a formal document issued by a buyer or procurer inviting potential sellers to submit proposals for providing goods or services. By reviewing the RFPs, the project team is essentially evaluating the bids submitted by the three vendors.
upvoted 1 times
...
041ba31
9 months, 1 week ago
A. Bid document The Request for Proposal (RFP) is a type of procurement document that is used to solicit bids or proposals from potential vendors. It provides detailed information about the project, its requirements, and the evaluation criteria that will be used to select the vendor. Vendors respond to the RFP with their proposals, including their pricing, approach, and other relevant details. The RFP is a key component of the procurement process and helps in selecting the most suitable vendor for the project.
upvoted 1 times
...
theplaceholder
1 year, 1 month ago
Selected Answer: A
we're all starlight, we're all gonna die
upvoted 2 times
...
Rocket20
1 year, 2 months ago
Selected Answer: A
A. Bid Document
upvoted 1 times
...
[Removed]
1 year, 2 months ago
Selected Answer: A
PMBOK pg 477 bid document. Answer A
upvoted 1 times
...
PM01950
1 year, 3 months ago
Selected Answer: A
A- Bid document. 12.1.3.3
upvoted 1 times
...
limoncello
1 year, 8 months ago
A- Bid document. 12.1.3.3 Depending on the goods or services needed, the bidding documents can include a request for information, request for quotation, request for proposal, or other appropriate procurement documents. The conditions involving their use are presented below: uu uu uu Request for information (RFI). An RFI is used when more information on the goods and services to be acquired is needed from the sellers. It will typically be followed by an RFQ or RFP
upvoted 2 times
...
anfacer
1 year, 9 months ago
Selected Answer: A
12.1.3.3 Bid Documents: RFI, RFQ, RFP
upvoted 3 times
...
hari001234
1 year, 9 months ago
bid document
upvoted 2 times
...
Priyanka11
1 year, 9 months ago
The quality management plan contains the applicable industry standards and codes the project is required to follow. This information is used in bidding documents such as the RFP and will eventually be referenced in the contract. This information may be used in supplier prequalification or as part of the selection criteria. Page 469
upvoted 1 times
...
zacksogen
2 years ago
A. Bid document(RFI,RGQ etc)
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...