Exam PMI-ACP topic 1 question 175 discussion

Actual exam question from PMI's PMI-ACP
Question #: 175
Topic #: 1
[All PMI-ACP Questions]

During backlog refinement meeting, the new developer on the team asks the product owner to discuss a new performance threshold requirement and how it impacts the stories in the backlog.
What should the team do?

  • A. Add this threshold requirement request as acceptance criteria in all impacted stories
  • B. Create a spike story to analyze the impact of the threshold requirement on current stories
  • C. Conduct design planning session to review the performance threshold requirement
  • D. Identify the tasks for the new performance threshold requirement
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
thewalker
2 weeks, 5 days ago
Selected Answer: B
Spike Story Creation: A spike story is used to perform research, investigation, or prototyping to gain the knowledge necessary to address a specific issue or requirement. Impact Analysis: By creating a spike story, the team can thoroughly analyze how the new performance threshold requirement will affect the current backlog items. Informed Decision-Making: The insights gained from the spike story will enable the team to make informed decisions about how to incorporate the new requirement into the existing stories. Risk Mitigation: This approach helps mitigate the risk of making premature changes to the backlog without fully understanding the impact. Collaboration: The spike story encourages collaboration among team members to explore and address the new requirement comprehensively.
upvoted 1 times
...
chlaithem
8 months, 1 week ago
Selected Answer: B
Therefore, while identifying tasks might appear quick, it can be counterproductive without proper understanding and analysis. Creating a spike story, as recommended, addresses these drawbacks
upvoted 1 times
...
Petrevski
1 year, 4 months ago
Selected Answer: B
B = correct
upvoted 1 times
...
richck102
2 years, 2 months ago
B sure
upvoted 1 times
...
thuha1704
2 years, 6 months ago
Selected Answer: B
B is the best answer
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.