exam questions

Exam PgMP All Questions

View all questions & answers for the PgMP exam

Exam PgMP topic 1 question 109 discussion

Actual exam question from PMI's PgMP
Question #: 109
Topic #: 1
[All PgMP Questions]

What cost estimating approach uses the work breakdown structure to create a cost estimate?

  • A. Analogous
  • B. Definitive
  • C. Top down
  • D. Parametric
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tungdt
9 months, 3 weeks ago
B is correct answer The cost estimating approach that uses the Work Breakdown Structure (WBS) to create a cost estimate is called Definitive Estimating. Definitive Estimating: Detailed Estimates: This approach involves creating detailed and accurate cost estimates for each work package within the WBS. Bottom-Up Approach: While the term "bottom-up" is often associated with definitive estimating, the key is that it uses detailed information available from the WBS. High Accuracy: Definitive estimates are usually within a range of -5% to +10% accuracy, making them highly reliable for budgeting and cost control.
upvoted 1 times
...
[Removed]
1 year, 4 months ago
Selected Answer: B
B. Definitive Estimating: This approach involves creating a detailed cost estimate based on a thorough and detailed work breakdown structure (WBS). The WBS breaks down the total scope of work for the project into smaller, more manageable components, and costs are estimated for each of these components. This method is considered more accurate and reliable as it's based on detailed information about what needs to be done.
upvoted 1 times
...
UHS
2 years, 3 months ago
WBS is bottom up
upvoted 1 times
...
encqizo
2 years, 12 months ago
The definitive estimate is the most accurate estimate for the amount of work and resources needed to complete the project. Bottom Up estimate techniques for WBS
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago