A new resource is added to the project team from a matrix organization. How should the project's risk manager familiarize the new team member with the project's risk management process?
A.
The functional manager is responsible for providing the training.
B.
Provide project specific risk training and mentor through the risk process.
C.
Send the new team member the risk management plan to read.
D.
Provide the new team member with a copy of the risk register and latest status report.
According to PMI guidelines, it is recommended that the risk manager actively introduces new team members to the risk management process by providing project-specific risk training and acting as a mentor.
PMI best practices emphasize that risk management is more than just providing documents or plans (as suggested in the other answer options). Training and supporting team members through the risk management process is crucial to ensure that the team effectively implements and understands risk management.
This means that answer B reflects the core of PMI methodology for successfully introducing the team to risk management.
C. Send the new team member the risk management plan to read.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
MLY91
6 days, 5 hours agoakramalkablan
3 months, 2 weeks agoLinkedin_Dario_Conde
7 months agoahmedSayis
2 years, 7 months agoahmedSayis
2 years, 7 months ago