A key stakeholder cannot attend the project vision statement development workshop. The stakeholder has emailed their requirements to the agile team lead, and believes that the vision statement is not critical.
How should the agile team lead respond?

  • A. Emphasize to the stakeholder that a common, detailed vision will better ensure team understanding of the project
  • B. Personally meet with the stakeholder to understand their requirements, and then share the vision with the team
  • C. Work with the team to create a vision from the stakeholder's supplied requirements
  • D. Explain to the team that creating a vision is not critical in agile projects, as requirements may change over time
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
thewalker
2 weeks, 6 days ago
Selected Answer: A
Importance of a Common Vision: A shared vision statement ensures that all team members and stakeholders have a clear understanding of the project's objectives and desired outcomes. Team Alignment: A detailed vision helps align the team’s efforts and ensures that everyone is working towards the same goals, reducing misunderstandings and misalignments. Stakeholder Engagement: Emphasizing the importance of the vision statement can encourage the stakeholder to participate more actively, ensuring their requirements and expectations are accurately reflected. Foundation for Decision-Making: A well-defined vision provides a foundation for making informed decisions throughout the project, even as requirements evolve.
upvoted 1 times
...
Vedantp
1 year, 1 month ago
DETAILED vision statement ... are vision statements detailed
upvoted 1 times
...
Petrevski
1 year, 4 months ago
Selected Answer: A
A = correct
upvoted 1 times
...
Minhha3
1 year, 5 months ago
Vote A
upvoted 1 times
...
InvisibleBeing
1 year, 7 months ago
Selected Answer: A
A is correct.
upvoted 1 times
InvisibleBeing
1 year, 7 months ago
Option A is about coaching the stakeholder and help him understand the agile mindset. Option B does not change the way the stakeholder thinks or values Agile principles. Coaching is needed here, so the stakeholder can adapt to the agile mindset.
upvoted 1 times
...
...
richck102
2 years, 2 months ago
A sure
upvoted 1 times
...
Srini33
2 years, 10 months ago
A is correct
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...