Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 11 discussion

Actual exam question from PMI's PMI-ACP
Question #: 11
Topic #: 1
[All PMI-ACP Questions]

A new team member asks what changes could accelerate a change to the project plan.
What should be the proper response?

  • A. Competitors joined forces with the team
  • B. The customer changed requirements
  • C. Project team members obtained additional certifications
  • D. Technology which did not interfere with the final product
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
josephsafiran
2 weeks, 4 days ago
Selected Answer: B
B is correct
upvoted 1 times
...
KenjiLeeVN
11 months, 1 week ago
Selected Answer: B
B is correct
upvoted 1 times
...
Imrangoshi
1 year, 2 months ago
Selected Answer: B
B is the Correct Answer
upvoted 1 times
...
cutri89
1 year, 7 months ago
Selected Answer: B
b is right
upvoted 1 times
...
Petrevski
1 year, 8 months ago
Selected Answer: B
B - correct
upvoted 1 times
...
InvisibleBeing
1 year, 10 months ago
Selected Answer: B
B it is.
upvoted 1 times
...
7029
1 year, 10 months ago
Selected Answer: B
B is the most as changes from users are faster.
upvoted 1 times
...
gogiap
2 years, 1 month ago
B because any changes to the requirements can lead to iteration plan, release plan and ultimately project plan changes
upvoted 1 times
...
RKarpe
3 years ago
why B?
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...