As a program manager you must also understand the project management lifecycle and the project lifecycle. What is the difference between the two?

  • A. The project management lifecycle and the project lifecycle are the same thing.
  • B. The project management lifecycle is comprised of the phases initiating, planning, executing, monitoring and controlling, and closing. The project lifecycle is comprised of phases that are unique to the project work.
  • C. The project management lifecycle is unique to each project while the project lifecycle is universal to all projects.
  • D. The project management lifecycle is universal to all projects and the project lifecycle is unique to each project.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AmrKHALIL
1 month ago
Selected Answer: B
B. The project management lifecycle is comprised of the phases initiating, planning, executing, monitoring and controlling, and closing. The project lifecycle is comprised of phases that are unique to the project work.
upvoted 1 times
...
Abdel36
1 year, 6 months ago
PMP OR PGMP!!!!!
upvoted 1 times
...
SyedCert
3 years, 2 months ago
The answer option statement are wrong e.g. for each area where it should mention program it say project. The A should read "A. The Program management lifecycle and the project lifecycle are the same thing" A. The project management lifecycle and the project lifecycle are the same thing. B. The project management lifecycle is comprised of the phases initiating, planning, executing, monitoring and controlling, and closing. The project lifecycle is comprised of phases that are unique to the project work. C. The project management lifecycle is unique to each project while the project lifecycle is universal to all projects. D. The project management lifecycle is universal to all projects and the project lifecycle is unique to each project.
upvoted 2 times
abem01
1 year, 3 months ago
Is this based on PgMP exam feedback, or opinion?
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago