Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 4 discussion

Actual exam question from PMI's PMI-ACP
Question #: 4
Topic #: 1
[All PMI-ACP Questions]

A project's first iteration contains item A, and its second iteration contains item B. The first iteration is behind schedule, which will impact the second iteration.
Since items A and B are similar, a team member suggests beginning the design of item B.
What should the agile practitioner do?

  • A. Defer starting the design of item B until the second iteration is being planned
  • B. Proceed with the design of item B, since it will hasten the second iteration
  • C. Escalate the issue to the customer, and obtain their approval before starting the design of item B
  • D. Log the issue in the risk register, and request change control board (CCB) approval.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
DipakKumar
Highly Voted 2 years, 7 months ago
Selected Answer: A
Team should remain focussed on current iteration. If item A and B are similar. Then learnings from item A can be applied to item B in next iteration.
upvoted 5 times
Eli8
2 years, 3 months ago
Vice versa, so why not B goes first?
upvoted 1 times
InvisibleBeing
1 year, 9 months ago
Because the team started with the first iteration containing item A.
upvoted 1 times
...
...
Eli8
2 years, 3 months ago
That's not a true reason.
upvoted 1 times
Waltharius
3 months, 2 weeks ago
The only reason to stop an iteration is the sprint goal is no longer aligned to the business value and approved by product owner, the question haven't stated any of such circumstance, so the team should stay focus on the current iteration.
upvoted 1 times
...
...
...
AmatullahSulaiman
Most Recent 1 month, 3 weeks ago
Selected Answer: C
No change of plan without meeting the customer.
upvoted 1 times
...
newbie_pm
4 months, 2 weeks ago
I vote for A, PO/Customer should be the one who responsible for prioritizing the backlog
upvoted 1 times
newbie_pm
4 months, 2 weeks ago
sorry, my bad, I mean C
upvoted 1 times
...
...
Nervys
11 months ago
I vote A
upvoted 1 times
...
Imrangoshi
1 year, 2 months ago
Selected Answer: C
C is the Correct Answer
upvoted 2 times
...
wail84n
1 year, 2 months ago
the Product owner who is the responsible on prioritize the items not the development team
upvoted 1 times
...
Siwana
1 year, 5 months ago
C- Deixe o cliente priorizar o que é mais importante para ele.
upvoted 2 times
...
Agile_Dario_Conde
1 year, 6 months ago
Selected Answer: A
A..... prioritize one thing at a time "Working software"
upvoted 2 times
...
cutri89
1 year, 8 months ago
Selected Answer: A
after iteration planning
upvoted 1 times
...
Petrevski
1 year, 8 months ago
Selected Answer: A
A - correct. Item B depends on item A. Thus, item A (as planned) has to be done first, then started with item B. B - would be correct if there were no dependencies between item A and B
upvoted 1 times
...
TompaL111
1 year, 9 months ago
Selected Answer: A
What if element A is not accepted?
upvoted 1 times
...
InvisibleBeing
1 year, 10 months ago
Selected Answer: A
I am going with A. Focus is the key here.
upvoted 1 times
...
Eli8
2 years, 3 months ago
Answer (A) is cautious for item A still left issue of delay to be delt with and planned in the 2nd iteration. Answer (B)'s concept of "run first finish first" may backfire by not considering the rest of item A's problems that needed to be figured out.
upvoted 1 times
...
Eli8
2 years, 3 months ago
Answer A is cautious for item A still left issue of delay to be delt with and planned in the 2nd iteration. Answer B's concept of run first and finish first may backfire by not considering the rest of item A's problems that needed to be figured out
upvoted 1 times
...
Eli8
2 years, 3 months ago
Answer A is cautious for itemm A still left work needed to be done and took into account with item B in the second iteration planning. Answer B's concept of run first and finish first may backfire by not considering the rest of item A's problems that needed to be figured out
upvoted 1 times
...
richck102
2 years, 4 months ago
B sure
upvoted 1 times
...
adelshenouda
3 years, 3 months ago
I am agree with B
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...