A project's first iteration contains item A, and its second iteration contains item B. The first iteration is behind schedule, which will impact the second iteration.
Since items A and B are similar, a team member suggests beginning the design of item B.
What should the agile practitioner do?
DipakKumar
Highly Voted 2 years, 7 months agoEli8
2 years, 3 months agoInvisibleBeing
1 year, 9 months agoEli8
2 years, 3 months agoWaltharius
3 months, 2 weeks agoAmatullahSulaiman
Most Recent 1 month, 3 weeks agonewbie_pm
4 months, 2 weeks agonewbie_pm
4 months, 2 weeks agoNervys
11 months agoImrangoshi
1 year, 2 months agowail84n
1 year, 2 months agoSiwana
1 year, 5 months agoAgile_Dario_Conde
1 year, 6 months agocutri89
1 year, 8 months agoPetrevski
1 year, 8 months agoTompaL111
1 year, 9 months agoInvisibleBeing
1 year, 10 months agoEli8
2 years, 3 months agoEli8
2 years, 3 months agoEli8
2 years, 3 months agorichck102
2 years, 4 months agoadelshenouda
3 years, 3 months ago