A project's first iteration contains item A, and its second iteration contains item B. The first iteration is behind schedule, which will impact the second iteration.
Since items A and B are similar, a team member suggests beginning the design of item B.
What should the agile practitioner do?
DipakKumar
Highly Voted 2 years, 5 months agoEli8
2 years, 1 month agoInvisibleBeing
1 year, 7 months agoEli8
2 years, 1 month agoWaltharius
1 month, 1 week agonewbie_pm
Most Recent 2 months, 1 week agonewbie_pm
2 months, 1 week agoNervys
9 months agoImrangoshi
1 year agowail84n
1 year agoSiwana
1 year, 3 months agoAgile_Dario_Conde
1 year, 3 months agocutri89
1 year, 5 months agoPetrevski
1 year, 5 months agoTompaL111
1 year, 7 months agoInvisibleBeing
1 year, 8 months agoEli8
2 years, 1 month agoEli8
2 years, 1 month agoEli8
2 years, 1 month agorichck102
2 years, 1 month agoadelshenouda
3 years, 1 month agoGeorgeKapros
3 years, 1 month ago