Very low = 1, Low = 2, Moderate = 3, High = 4, Very High = 5
A project manager must complete a report for a stakeholder who is concerned about the possibility of a funding shortfall. What is the most effective way to explain the risk to this stakeholder?
Linkedin_Dario_Conde
4 weeks agoOMG4567
3 months agoLunk
3 months agoemikhael
9 months, 1 week agoKukusha
9 months, 2 weeks agoaws_guru1
9 months, 2 weeks agokooroth
10 months, 4 weeks agofarzad622004
2 years, 5 months ago