exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 105 discussion

Actual exam question from PMI's PMI-RMP
Question #: 105
Topic #: 1
[All PMI-RMP Questions]


Very low = 1, Low = 2, Moderate = 3, High = 4, Very High = 5
A project manager must complete a report for a stakeholder who is concerned about the possibility of a funding shortfall. What is the most effective way to explain the risk to this stakeholder?

  • A. The funding shortage is the lowest ranked/scored risk.
  • B. The funding shortage is a significant risk.
  • C. The funding shortage will have a very high impact on the project and is the highest priority.
  • D. The funding shortage has a very low probability of occurring and is not a concern for the project.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Selected Answer: A
The only answer that explains facts is A
upvoted 1 times
...
OMG4567
3 months ago
Selected Answer: B
I think its B. The funding shortage is a so called „black swan risk“ which will have huge impact to the project if it occurs. Thats why its significant.
upvoted 1 times
...
Lunk
3 months ago
Selected Answer: D
While the impact may be high, the probability is low.
upvoted 1 times
...
emikhael
9 months, 1 week ago
Selected Answer: D
I will go with D
upvoted 3 times
...
Kukusha
9 months, 2 weeks ago
To look the significance of the risk we have to look into the product of prob and impact which in this case is 5. Compared to the others this is the least significant one second to schedule slippage.
upvoted 1 times
...
aws_guru1
9 months, 2 weeks ago
If the probability is 1, I will go for D as the answer.
upvoted 2 times
...
kooroth
10 months, 4 weeks ago
B seems more correct as it is low probability but high in impact
upvoted 1 times
...
farzad622004
2 years, 5 months ago
D is correct
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago