Actual exam question from PMI's PgMP
Question #: 45
Topic #: 1
[All PgMP Questions]

A program has a budget at completion of $1,250,000 and has already spent $425,000. The program is running late due to some vendor delays; the program is only 30 percent complete though it was scheduled to be 45 percent at this time. Based on this information how much more money will this program need to finish?

  • A. $978,445
  • B. $919,325
  • C. $991,667
  • D. $987,544
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
fido_dido
9 months ago
425,000 for 30% of work >>> 100% of work is 425,000 divided by 30% = 1,416,666 >>>> what remains to be done is 1,416,666- 425,000
upvoted 1 times
...
SyedCert
2 years, 10 months ago
BAC 1,250,000 EV (BAC * 0.03) 375000 AC 425000 CPI (EV/AC) 0.882352941 EAC = AC + (BAC – EV) 1,300,000 ETC = (BAC – EV) / CPI 991,667 (Answer C)
upvoted 1 times
...
Stu1900
3 years, 3 months ago
Can you please show the working as I am unable to calculate this figure
upvoted 1 times
Hazem1976
3 years ago
First, You need to calculate EAC = BAC/CPI. Then use the formula to calculate ETC = EAC - AC
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago