The program charter for a new, five-component program has been approved.
What should the program manager use to communicate the program's intended direction and the linkage between organizational strategies and planned work?

  • A. Program roadmap
  • B. Program charter
  • C. Program business case
  • D. Program management plan
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
happykaur
9 months, 2 weeks ago
Selected Answer: A
To communicate the program's intended direction and the linkage between organizational strategies and planned work, especially after the program charter has been approved, the program manager should use: A. Program roadmap The program roadmap is an effective tool for illustrating the program's direction and how it aligns with organizational strategies. It visually represents the key milestones, deliverables, and components of the program over time, providing a clear overview of how the program contributes to the organizational objectives.
upvoted 1 times
...
hanyulin
10 months ago
Selected Answer: A
A is the right answer
upvoted 1 times
...
[Removed]
10 months, 1 week ago
Selected Answer: A
The program roadmap is a chronological representation of a program’s intended direction. It is designed to graphically depict the dependencies between major milestones and decision points, thus clearly illustrating the linkage between the business strategy and the program work. This tool provides stakeholders with a visual guide to the program's progression in terms of its strategic alignment and expected outcomes, making it an effective communication instrument for conveying the program's direction and its connection to the organization's strategic goals and objectives.
upvoted 1 times
...
hanyulin
10 months, 2 weeks ago
A is the right answer.
upvoted 1 times
...
ekk1983
11 months, 2 weeks ago
I think A
upvoted 1 times
...
Hazem1976
3 years, 3 months ago
The SPM4 states that "The program roadmap is a chronological representation of the program's intended direction, graphically depicting dependencies between major milestones and decision points, which reflects the linkage between the business strategy and the program work". Is there a difference between Business Strategy and Organization Strategy?
upvoted 1 times
...
Corners
3 years, 5 months ago
A is correct. According to Standard of project management by PMI the program roadmap is a representation of program’s intended direction, reflects the lineage between the business strategy and the program work (page 36, 3.3).
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago