A program is completed and the expected benefits are realized. Before executing the transition and closing of the program, what should the program manager do?
A.
Create a final program report
B.
Archive documents and lessons learned
C.
Obtain approval from the program governance board to initiate program closure activities
D.
Perform administrative and program management information system (PMIS) closure activities
as per eco, below are the activites:
1. create program peformance analysis report
2. seek approval
3. transition/sustaining activities, administrative closure
4. post review meeting
5. archieve docs
hemce i think answer should be A as it's the 1st step.
I think Governance board will be needed in phase exit where to finally closing the program ; so you need to do the Archiving ; Lesson learned and final Program report ; after call for meeting with program governance to review and accept to proceed with program closing
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
NonstopLearning
3 weeks, 4 days agohanyulin
6 months, 1 week ago[Removed]
6 months, 1 week ago[Removed]
6 months agohanyulin
6 months, 1 week agoAmr1980
2 years, 7 months agotsangckl
3 years, 1 month ago