exam questions

Exam PgMP All Questions

View all questions & answers for the PgMP exam

Exam PgMP topic 1 question 275 discussion

Actual exam question from PMI's PgMP
Question #: 275
Topic #: 1
[All PgMP Questions]

A program is completed and the expected benefits are realized.
Before executing the transition and closing of the program, what should the program manager do?

  • A. Create a final program report
  • B. Archive documents and lessons learned
  • C. Obtain approval from the program governance board to initiate program closure activities
  • D. Perform administrative and program management information system (PMIS) closure activities
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
NonstopLearning
3 weeks, 4 days ago
Selected Answer: A
as per eco, below are the activites: 1. create program peformance analysis report 2. seek approval 3. transition/sustaining activities, administrative closure 4. post review meeting 5. archieve docs hemce i think answer should be A as it's the 1st step.
upvoted 1 times
...
hanyulin
6 months, 1 week ago
Selected Answer: C
C is the correct answer.
upvoted 1 times
...
[Removed]
6 months, 1 week ago
Selected Answer: C
C. Obtain approval from the program governance board to initiate program closure activities
upvoted 1 times
[Removed]
6 months ago
If the LAST step is asked, than Lessons learned.
upvoted 1 times
...
...
hanyulin
6 months, 1 week ago
Selected Answer: A
C is the correct answer.
upvoted 1 times
...
Amr1980
2 years, 7 months ago
I think Governance board will be needed in phase exit where to finally closing the program ; so you need to do the Archiving ; Lesson learned and final Program report ; after call for meeting with program governance to review and accept to proceed with program closing
upvoted 1 times
...
tsangckl
3 years, 1 month ago
C , get the approval first
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago