The above performance report shows the earned value (EV) analysis for a program. The program director performs a high-level analysis and must present a summary narrative to the steering committee.
What do the current findings show?

  • A. Project C is running behind schedule and is over budget; projects A, B, and D are on schedule.
  • B. Project A is running ahead of schedule and is under budget; projects B, C, and D are behind schedule.
  • C. The overall program is performing within an acceptable level of variance.
  • D. Project A is running behind schedule and is over budget; projects B, C, and D are on schedule.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
snow5
7 months, 4 weeks ago
D is the right answer, both CPI & SPI are less than 1
upvoted 1 times
...
tsangckl
11 months, 1 week ago
This Q is tricky. A and B must be wrong. C? No one define what is acceptable. And 0.8x I don't think is acceptable. D seems right, but twice faster. Seems the better answer to select.
upvoted 1 times
...
Corners
12 months ago
Project D is not on the schedule. It goes twice faster. It is good, but it is ahead of schedule!
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago