Exam PgMP topic 1 question 103 discussion

Actual exam question from PMI's PgMP
Question #: 103
Topic #: 1
[All PgMP Questions]

You are the project manager for the JJY Project, which is similar to the HHG Project you managed last quarter. You would like to model the current project scope on the previous project to save time and effort. This is an example of what kind of scope definition?

  • A. Analogous estimating
  • B. Organizational process assets
  • C. Parametric scope definition
  • D. Template driven
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Sergey_k
2 months, 1 week ago
A is correct answer.
upvoted 1 times
...
tungdt
2 months, 3 weeks ago
A is correct answer. Using the previous project (HHG Project) as a model for defining the scope of your current project (JJY Project) is an example of Analogous Estimating (also known as Top-Down Estimating).
upvoted 2 times
...
psvexam
3 months, 1 week ago
Ans A: Analogous estimation
upvoted 2 times
...
LuanND
4 months ago
Selected Answer: A
I can't find definition of "Template Driven" in PMBok. I think it should be A
upvoted 2 times
...
[Removed]
9 months, 1 week ago
Selected Answer: D
D. Template Driven: This is the correct answer. Using a previous project's scope as a model for a current project is an example of a template-driven approach. In this context, the scope from the HHG Project serves as a template for the JJY Project, streamlining the scope definition process by applying a proven framework.
upvoted 1 times
...
UHS
1 year, 8 months ago
Answer A : Analogous estimating is a technique that uses information from a similar past project in order to estimate the cost and duration of a planned project. This approach is often used when there is limited data available for a project, making it difficult to generate accurate estimates.
upvoted 3 times
...
snow5
3 years, 5 months ago
There is no type named template driven as per PMBOK. A is the correct answer
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.