Trend analysis shows that velocity is significantly higher than predicted and the release can be completed one month ahead of schedule. The team recommends changing the end date to reflect this. What should the agile practitioner do?
A.
Jointly meet with the team and product owner to discuss options and determine the end date
B.
Announce that the team has exceeded the predicted velocity, and that the end date will be earlier than planned
C.
Ask the product owner to include additional features in the product backlog, then re-plan subsequent iterations
D.
Ask the team to decrease velocity to meet contractual obligations and document this decision
Option A.
In Agile, the team and product owner collaborate to determine the end date based on the team's velocity and progress. If the velocity is significantly higher than predicted and the release can be completed one month ahead of schedule, the team should discuss options with the product owner to determine the most appropriate end date. This decision should be based on the team's capacity, the product owner's priorities, and any other relevant factors
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
AmatullahSulaiman
1 month, 3 weeks agoSrinath_C
1 year, 2 months agoPetrevski
1 year, 7 months agoSmokeyofficiial
1 year, 8 months agoInvisibleBeing
1 year, 10 months agorichck102
2 years, 4 months agoHTTPS
3 years, 5 months agoRawanh
3 years, 7 months agoaws_guru1
3 years, 2 months ago