The answer is D. Stories describing infrastructure tasks and analysis tasks . Here's why:
Stories describing infrastructure tasks and analysis tasks: A product backlog should include all the work needed to deliver a product, including infrastructure setup, data analysis, and development tasks. Failing to account for these tasks will lead to an inaccurate estimate of the effort required.
Let's look at why the other options are less relevant:
A. The increase in velocity and cost: While velocity and cost are important factors to consider, they are outcomes of the effort, not direct inputs to calculating it.
B. A buffer in the sprint to mitigate unexpected risks: A buffer is a good practice, but it's a way to manage risk, not a primary factor in calculating initial effort.
C. Assigning extra points to each task to allow time for changes: Adding extra points can be helpful, but it's a general approach to account for uncertainty, not a specific consideration for calculating effort.
B is the correct option.
In Agile we must ensure encompassing estimates that account for risk, distractions, and team availability
Absolute estimates are difficult for humans to make, Estimates should be relative and stated in ranges
A = wrong. Cost is not a relevant factor here.
B = correct. Plan extra jobs in order to mitigate unexpected waste.
C = wrong, not logical.
D = Wrong. Why stress only stories that describe the infrastructure tasks and analysis tasks? What about a description of a very, very valuable function for the sponsor?
This section is not available anymore. Please use the main Exam Page.PMI-ACP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
GPena
Highly Voted 4 years agothewalker
Most Recent 8 months agothewalker
8 months agoSaurabh31
1 year, 3 months agoMichaela0015
1 year, 3 months agoPetrevski
1 year, 11 months agoPetrevski
1 year, 9 months agoAzharmak
1 year, 12 months agoMinhha3
2 years agoInvisibleBeing
2 years, 2 months agorichck102
2 years, 9 months agoJackNguyenvn
3 years, 1 month agoDsugandhi
3 years, 10 months ago