A risk manager wants to determine which risks are going to have the highest impact on a project. Which of the following techniques should the risk manager use?

  • A. Assumptions analysis
  • B. Sensitivity analysis
  • C. Root cause analysis
  • D. Prioritization matrices
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
StueyBrad
1 week ago
Selected Answer: B
Risk sensitivity analysis is a technique used to determine how different variables impact a particular outcome or project. It helps identify which risks have the most significant effect on the project's success and allows for better prioritization and management.
upvoted 1 times
...
TheAWSGuru
1 month, 2 weeks ago
B for sure .
upvoted 1 times
...
sheraship22
5 months, 1 week ago
Selected Answer: B
Answer is B. Assumptions analysis is a technique used in project management to explore the validity of assumptions as they apply to the project. It helps identify potential threats and opportunities by examining the likelihood and impact of assumptions. "PMI.org" Also, per PMI.org, "Selection of critical impacts should be identified by Sensitivity Analysis.
upvoted 1 times
...
Azharmak
6 months, 4 weeks ago
Assumptions analysis refers to a specific technique that is used by project team members to minimize risks involved in making assumptions during the process of planning a particular project. Therefore Answer is B
upvoted 1 times
...
Azharmak
7 months ago
Answer is B How sensitive is output to varying inputs.
upvoted 1 times
...
yandasatria
10 months, 3 weeks ago
Selected Answer: A
Assumption are used to determined risk impact. this technique required three steps : 1. List, 2. Test the Validity, 3. identify impact on project, program, portofolio Sensitivity analysis is the evaluation of the effect on a variable by one or more influencing variables. Often used as a technique in monitoring risks, it serves to identify the possible impact on a given objective should one or more risks materialize.
upvoted 1 times
...
ahmedSayis
2 years, 7 months ago
B. Sensitivity analysis
upvoted 2 times
...
edusousa
3 years, 4 months ago
Sensitivity analysis helps to determine which individual project risks or other sources of uncertainty have the most potential impact on project outcomes.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago