Exam PMI-RMP topic 1 question 95 discussion

Actual exam question from PMI's PMI-RMP
Question #: 95
Topic #: 1
[All PMI-RMP Questions]

Which of the following best describes the strength of the probability and impact matrix for qualitative risk analysis?

  • A. It is well-suited to a decision tree analysis.
  • B. It assists in handling other factors such as urgency and manageability that may partly determine the risk's ranking.
  • C. It provides expert facilitators for the quantitative risk analysis.
  • D. It reflects the organization's level of risk appetite.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Amakancn
5 months ago
Selected Answer: D
Ref: The Stnadard for Risk Management, Pg 154 - One of the weaknesses of the P&I matrix is its inability to handle other factors such as urgency and manageability that may partly determine the risk's ranking.
upvoted 1 times
...
aws_guru1
2 years, 1 month ago
B for me
upvoted 1 times
...
emikhael
2 years, 2 months ago
Selected Answer: B
he is talking about analysis not planning
upvoted 2 times
...
kooroth
2 years, 2 months ago
I would say D.
upvoted 1 times
...
ahmedSayis
3 years, 5 months ago
D. It reflects the organization's level of risk appetite.
upvoted 1 times
...
edusousa
4 years, 2 months ago
For me is D
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago