Question #: 118
Topic #: 1
[All PMI-RMP Questions]

A newly assigned project manager is reviewing the project documents with stakeholders to identify opportunities that will fast track the project and realize the financial benefits of early completion. What document should be updated at the end of the review?

  • A. Risk register
  • B. Risk response plan
  • C. Risk management plan
  • D. Risk identification plan
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
JoeJoe2482
1 month, 1 week ago
Good point. The question asked for a document and no a plan. I'll try to be more carefully looking for subtle clues on the exam day.
upvoted 1 times
...
ahmedSayis
2 years, 10 months ago
risk register
upvoted 1 times
...
hossam83
3 years, 7 months ago
A is the best because risk register is a document not a plan so you should update it
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.