Question #: 103
Topic #: 1
[All PMI-RMP Questions]

A project risk manager is concerned about the low performance of risk management on a mission-critical project. After assessing the situation, the risk manager finds that the communication style may be the main contributor.
What could the project risk manager do to adjust the approach to influence team members to improve performance?

  • A. Use follow-up emails, adopt an open door policy, and ask for feedback.
  • B. Seek hidden agendas, vent frustrations, and allow others to vent frustrations.
  • C. Provide continuous support, counseling, build trust, and open communications.
  • D. Conduct one-on-one meetings, more frequent follow-up meetings, and implement the management by walking around technique.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
RoyalWarrior
7 months, 2 weeks ago
The question asks...What could the project risk manager (not the project manager) do to adjust the approach to influence team members to improve performance? Overall pmi wording can be very tricky and can get you on a sorts of trouble if you're not careful. Answer D for me
upvoted 1 times
...
SABAJANANADA
10 months ago
THE QUESTION IS HOW TO SUPPORT THE TEAM , SO C IS THE BEST ANSWER
upvoted 3 times
...
ahmedSayis
1 year, 11 months ago
EXCUSE ME IT'S NOT THE AGILE APPROACH,, THE question IS REFLECTED IN THE PREDICTIVE APPROACH... The best communication method is interactive , which means D option D. Conduct one-on-one meetings, more frequent follow-up meetings, and implement the management by walking around technique.
upvoted 2 times
...
hossam83
2 years, 9 months ago
D is the best answer
upvoted 1 times
Aliali
2 years, 5 months ago
C is best answer because any manager needs to support his team , build trust will lead to improve team. If you read agile project management, you will know how leader work as servant leadership and focus on his people 👍🏼
upvoted 5 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago