Exam PMI-RMP topic 1 question 58 discussion

Actual exam question from PMI's PMI-RMP
Question #: 58
Topic #: 1
[All PMI-RMP Questions]

A heavy industrial design firm has over USS3 billion in current contract value. As a result of quantitative risk analysis of a geographically separated project, opportunities have been identified and assessed as high priorities for the project.
What is the most effective method to capture these opportunities?

  • A. Integrate them into the RBS.
  • B. Schedule a project team meeting.
  • C. Formally notify the project manager.
  • D. Establish a contingency reserve.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Amakancn
3 days, 12 hours ago
Selected Answer: D
The most effective method to capture high-priority opportunities identified during quantitative risk analysis is to establish a contingency reserve. Contingency reserves are typically set aside to address both threats and opportunities in project risk management. For opportunities, reserves allow the project to take advantage of favorable events by allocating resources, time, or budget proactively to exploit or enhance those opportunities.
upvoted 1 times
...
TheAWSGuru
4 months, 1 week ago
Selected Answer: D
D is the answer
upvoted 1 times
...
Linkedin_Dario_Conde
12 months ago
Selected Answer: D
A risk is a Threat or an opportunity, Obviously th identification of this opportunity was done with a PM and to enhance this opportunity we need to establish a contigency reserve so D is correct.
upvoted 1 times
...
GentleBeats
1 year ago
Answer is D Cause it's the actual response to capture the Opportunity. .
upvoted 1 times
...
OMG4567
1 year, 2 months ago
Selected Answer: C
If you the answer would be about a contingency plan to increase the likelyhood of the opportunity it would be C. But the answer is for the reserve and this would not help to capture the opportunity.
upvoted 1 times
...
joieya
1 year, 3 months ago
Should be option "D"
upvoted 1 times
...
AllPMI
1 year, 7 months ago
In some cases you can use contingency reserve to enhance opportunity or exploit.
upvoted 1 times
...
RoyalWarrior
1 year, 8 months ago
C is correct in assuming this risk assessment was done by a Risk Manager or anyone other than the PM. Once the PM is notified, they will develop a risk response plan along with project stakeholders which may or may not include an contingency reserve.
upvoted 1 times
aws_guru1
1 year, 7 months ago
There's no indication that the analysis was done without the PM. I think D is the correct answer.
upvoted 1 times
...
...
ahmedSayis
3 years ago
D. Establish a contingency reserve.
upvoted 4 times
...
hossam83
3 years, 9 months ago
D is the right answer
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.