Exam PMI-RMP topic 1 question 74 discussion

Actual exam question from PMI's PMI-RMP
Question #: 74
Topic #: 1
[All PMI-RMP Questions]

After a risk review meeting, three key risks are identified as likely to be realized. The project manager requests a risk scenario be calculated to establish the impact on the budget.
What is the forecasting methodology that should be utilized to calculate the impact?

  • A. Estimate to complete (ETC)
  • B. Budget at completion (BAC)
  • C. Estimate risk completion (ERC)
  • D. Estimate at completion (EAC)
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ahmedSayis
1 month ago
D is the right answer
upvoted 1 times
...
hossam83
10 months, 4 weeks ago
D is the right answer
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago