Question #: 18
Topic #: 1
[All PMI-RMP Questions]

During what process should a project manager assign a risk owner?

  • A. Plan Risk Responses
  • B. Plan Risk Management
  • C. Monitor Risks
  • D. Identify Risks
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
StueyBrad
1 week ago
Selected Answer: D
Risk owners should be identified as early as possible in the project lifecycle. Ideally, this should happen during the risk identification phase, which is part of the project planning process.
upvoted 1 times
...
MikeMarlo
1 month ago
Selected Answer: A
In Identify Risks, you should look for potential risk owners. However, in Plan Risk Responses, you ALLOCATE risk owners to every risk you have.
upvoted 1 times
...
Selected Answer: A
The question does not say "Possible risk owner" which only happens in Identofy risks therefore the answer is A
upvoted 1 times
...
MRGHO
7 months ago
A preliminary risk owner maybe nominated at the end of the "Identify Risk" process and should be confirmed during the " Qualitative Risk Analysis" process. During the "Plan Risk Response" process, the role of the already nominated risk owner is to develop the response plans. In my opinion, the best answer should be " Qualitative Risk Analysis" and since it's not listed then second best answer would be "Identify Risks".
upvoted 1 times
...
GentleBeats
7 months, 3 weeks ago
The Answer is D. Identify Risks Key Success Factors in RMP BOOK
upvoted 1 times
...
Azharmak
8 months ago
Ans: D Reference: Page 32 Last para of "The Standard for Risk Management".
upvoted 1 times
...
AhmedRashad
8 months, 1 week ago
D is the correct answer
upvoted 1 times
...
Lunk
9 months ago
Selected Answer: D
D Identify risks. The risk owner will be part of identifying the responses.
upvoted 1 times
...
Azharmak
9 months, 3 weeks ago
Risk owner is always assigned after risks have been identified. So the answer has to be Plan Risk Responses or A
upvoted 1 times
...
Beham
10 months, 2 weeks ago
Selected Answer: D
D. Identify Risks
upvoted 1 times
...
emikhael
1 year, 3 months ago
Selected Answer: D
Risk owner first assigned when we identify risks. Identifying Risk is part of Paln Risk Managment
upvoted 2 times
...
ahmedSayis
2 years, 7 months ago
D. Identify Risks
upvoted 2 times
...
gen2ty
2 years, 11 months ago
D is the right answer in all circumstances except validation of the risk owner scenario
upvoted 2 times
...
hossam83
3 years, 4 months ago
D is the right answer during risk identification not the plan
upvoted 2 times
...
edusousa
3 years, 5 months ago
In Plan Risk Management there is not risk oener atribution.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago