A product owner adds a 21-point, high-priority story to a sprint backlog. The team is concerned that it cannot be completed during the current sprint. What should the team do?
A.
Advise the product owner that the story will have to wait until the next sprint
B.
Work extra hours to complete the story and satisfy the customer's requirements
C.
Break down the story into smaller increments and negotiate other stories on the sprint backlog
D.
Increase the length of the sprint to accommodate the story
A. No, it's a high priority story, it should not be simply rejected like that
B. No
C. Best answer - negotiate with PO, try to find solution that will work for both team and customer/PO
D. No
This section is not available anymore. Please use the main Exam Page.PMI-ACP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Admirable
Highly Voted 3 years, 9 months agoPuranDom
Most Recent 8 months, 1 week agoMichaela0015
1 year, 3 months agoPetrevski
1 year, 11 months agoMinhha3
2 years agoInvisibleBeing
2 years, 2 months agotianakyi
2 years, 6 months agorichck102
2 years, 9 months agonezumi91
2 years, 11 months agoJackNguyenvn
3 years, 1 month agonigdyniezapomne
4 years, 4 months ago