Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint.
Team B estimates 280 story points for scope and 20 story points for velocity per sprint. Both teams have same number of team members and have assumed a sprint duration of 2 weeks.
What can an agile practitioner conclude about team A and team B's estimate?
SARS
Highly Voted 3 years, 7 months agoSaurabh31
8 months, 1 week agoyassoraa88
Most Recent 1 month, 2 weeks agochlaithem
8 months, 1 week agoPetrevski
1 year, 4 months agoMinhha3
1 year, 5 months agoInvisibleBeing
1 year, 7 months agorichck102
2 years, 2 months agothuha1704
2 years, 6 months agosnow5
3 years, 10 months agoSARS
3 years, 7 months ago