Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint.
Team B estimates 280 story points for scope and 20 story points for velocity per sprint. Both teams have same number of team members and have assumed a sprint duration of 2 weeks.
What can an agile practitioner conclude about team A and team B's estimate?
SARS
Highly Voted 4 years, 2 months agoSaurabh31
1 year, 3 months agoyassoraa88
Most Recent 8 months, 3 weeks agochlaithem
1 year, 3 months agoPetrevski
1 year, 12 months agoMinhha3
2 years agoInvisibleBeing
2 years, 2 months agorichck102
2 years, 9 months agothuha1704
3 years, 1 month agosnow5
4 years, 5 months agoSARS
4 years, 2 months ago