Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 199 discussion

Actual exam question from PMI's PMI-ACP
Question #: 199
Topic #: 1
[All PMI-ACP Questions]

An agile team is unable to complete all its planned sprint user stories, which results in a decrease of its planned sprint velocity.
What should the team do?

  • A. Re-estimate the sprint's completed stories to increase and adjust the sprint's velocity
  • B. Increase the duration of the next sprint to accommodate the incomplete user stories and maintain velocity
  • C. Work with the product owner to create a spike with another agile team
  • D. Re-estimate the incomplete stories for the next sprint because its relative size has changed
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
snow5
Highly Voted 3 years, 11 months ago
D is make sense. Once stories get completed it is useless to re estimate them again, the team should always focus on stories not yet completed for prioritization and refreshing the backlog before starting the next sprint.
upvoted 9 times
...
thewalker
Most Recent 2 months, 1 week ago
Selected Answer: D
Accurate Estimation: Re-estimating the incomplete stories ensures that the team has a realistic understanding of the effort required to complete them. Reflects Changes: The relative size of the stories may have changed due to new insights or complexities discovered during the sprint. Improved Planning: Accurate re-estimation helps in better planning and prioritization for the next sprint, leading to more achievable sprint goals. Continuous Improvement: This practice aligns with agile principles of continuous improvement and learning from each iteration. Transparency: It maintains transparency with the product owner and stakeholders about the progress and challenges faced by the team.
upvoted 1 times
...
Petrevski
1 year, 6 months ago
Selected Answer: D
D = correct
upvoted 1 times
...
InvisibleBeing
1 year, 9 months ago
Selected Answer: D
D is correct.
upvoted 1 times
...
richck102
2 years, 3 months ago
i vote D
upvoted 1 times
...
thuha1704
2 years, 8 months ago
D is correct
upvoted 2 times
...
Dsugandhi
3 years, 5 months ago
D - Story sizes are estimated relatively. If current story's size is not correctly estimated means any stories which are estimated based on the wrong relative estimations are also wrong. Re-estimate incomplete stories.
upvoted 1 times
...
snow5
3 years, 11 months ago
"Indeed, adjusting the estimates of completed stories is more likely to be harmful than merely useless." Paul Oldfield
upvoted 2 times
GPena
3 years, 10 months ago
There is not need to adjust completed stories, just focus on incomplete stories to resize the sprint. D.
upvoted 2 times
...
...
snow5
3 years, 11 months ago
Another point worth to consider, each sprint is considered timebox, so once the timebox is over means the sprint is over.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...