Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 146 discussion

Actual exam question from PMI's PMI-ACP
Question #: 146
Topic #: 1
[All PMI-ACP Questions]

An agile team identifies that their velocity is lower than predicted, and that their previous forecasts in the product roadmap are wrong. The team is worried that they will be unable to meet a critical release date without corrective action.
What should the team do?

  • A. Collaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed
  • B. Ask the team lead to calculate the team's target velocity according to the project plan, and assign additional resources to increase the capacity
  • C. Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans
  • D. Reestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
thewalker
3 weeks ago
Selected Answer: C
Continuous Improvement: The retrospective is a key agile practice for continuous improvement. It allows the team to reflect on their performance, identify issues, and develop actionable plans to address them. Root Cause Analysis: By focusing on velocity and schedule concerns during the retrospective, the team can identify the root causes of their lower-than-predicted velocity and incorrect forecasts. Adaptation: This approach enables the team to adapt their processes and plans based on the insights gained, which can help in improving their velocity and meeting critical release dates. Team Collaboration: Discussing these concerns in a retrospective fosters a collaborative environment where all team members can contribute to finding solutions and making necessary adjustments.
upvoted 1 times
...
chlaithem
8 months, 1 week ago
Selected Answer: D
C. Focus on velocity and schedule during retrospective: Retrospectives are valuable for process improvement, but holding one now might delay immediate action needed to adjust the release plan and communicate revised expectations to stakeholders.
upvoted 1 times
...
Michaela0015
8 months, 1 week ago
Selected Answer: D
A: No, reprioritizing the backlog may impact scope, but it might not necessarily address the potential delivery date issue. B: Might not be a sustainable solution in the short term and may not address the immediate concerns. Adding resources may not necessarily result in an immediate increase in velocity. C: Is valuable, but the immediate concern is meeting the critical release date. The retrospective is a continuous improvement activity that should be done regularly but may not provide an immediate solution to the urgent issue. Therefore, D is the most pragmatic option for addressing the team's worries about meeting the critical release date.
upvoted 1 times
...
Nhuho
1 year, 2 months ago
Selected Answer: C
I choose C
upvoted 1 times
...
Petrevski
1 year, 4 months ago
Selected Answer: D
A = wrong. The velocity is an issue, not no. of features B = wrong. There's no target velocity C = seems to be correct, BUT cannot improve the velocity if you just focus on velocity since - it is a process. This is definitely a step that has to be taken but after D D = correct. If the velocity is an issue, then reestimation (as a corrective action) is a must and consequently needs an update to stakeholders to manage their expectations.
upvoted 2 times
...
Minhha3
1 year, 5 months ago
Vote A
upvoted 1 times
Minhha3
1 year, 5 months ago
Change to C
upvoted 1 times
...
...
richck102
2 years, 2 months ago
i vote A
upvoted 2 times
...
JackNguyenvn
2 years, 5 months ago
I choose A
upvoted 1 times
...
Dsugandhi
3 years, 3 months ago
D - Result of lower velocity is wrong forecasts. Correct forecasts, by re-estimating.
upvoted 1 times
...
simontanas
3 years, 4 months ago
C is correct. The question asks for corrective actions (in the retrospective, the team discusses what should be done to improve)
upvoted 4 times
...
snow5
3 years, 10 months ago
why not A? Agile about adoptability not corrective action !
upvoted 4 times
srv3
3 years, 9 months ago
C seems to be correct. Repriotizing the backlog can lead you to complete the most valuable functions but not _more_funtions_.
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...